TEA BREWING

1.Begin each brew cycle with a clean empty brew funnel and server. (Be sure the server lid doesn’t interfere with the flow of dilution water.)

2.Insert a BUNN filter into the funnel.

3.Pour the packet of loose fresh tea leaves into the filter. Approximately three to five ounces is recommended for three gallons of beverage.

4.Level the bed of tea leaves by gently shaking.

5.Slide the funnel into the funnel rails until it stops.

6.The ON/OFF must be ON. Select which batch size to brew.

7.Momentarily press and release the assigned BREW button. There may be certain situations in which the brew cycle will not begin when BREW is pressed:

a.SWITCH NOT ON - ON/OFF must be ON.

b.BREW TEMPERATURE TOO LOW – wait until heated or cancel BREW LOCKOUT option (Page 17).

c.CHECK FUNNEL – remove funnel, empty previously brewed leaves and replace with fresh tea leaves.

d.DISABLED - select different brew button or batch size.

8.If none of the above messages are displayed, the display will read NOW BREWING and show the time re- maining in the brew cycle.

9.Following the brew will be a countdown of drip time DRIPPING which shows the time remaining until the tea no longer drips from the funnel tip.

10.Carefully remove the brew funnel and discard the tea leaves and filter only after visible dripping stops.

COFFEE BREWING

WITHOUT A SMART FUNNEL AND G9-2T DBC GRINDER:

1.Begin each brew cycle with a clean empty brew funnel.

2.Insert a BUNN filter into the funnel.

3.Pour the fresh coffee into the filter and level the bed of grounds by gently shaking.

4.Slide the funnel into the funnel rails until it stops.

5.Place an empty server under the funnel.

6.The ON/OFF must be ON. Select the FULL batch size.

7.Momentarily press and release the assigned BREW button. There may be certain situations in which the brew cycle will not begin when BREW is pressed:

a.SWITCH NOT ON - ON/OFF must be ON.

b.BREW TEMPERATURE TOO LOW – wait until heated or cancel BREW LOCKOUT option (Page 17).

c.CHECK FUNNEL – remove funnel, empty previously brewed grounds and replace with fresh.

d.DISABLED - select different brew button or batch size.

e.COFFEE FUNNEL? – appears when brew volume is greater than 86.0 oz. (2.54 L) and pulse brew is disabled. Check to make sure the correct funnel is in place, and then press BREW again.

8.If none of the above messages are displayed, the display will read NOW BREWING and show the time remain- ing in the brew cycle.

9.Following the brew will be a countdown of drip time DRIPPING which shows the time remaining until the coffee no longer drips from the funnel tip.

10.Carefully remove the brew funnel and discard the grounds and filter only after visible dripping stops.

WITH A SMART FUNNEL AND G9-2T DBC or MHG GRINDER:

1.Select the small batch size on the grinder.

2.Insert a BUNN filter into the funnel.

3.Grind the selected amount of fresh coffee into the Smart Funnel using the G9-2T DBC or MHG with Smart Funnel operation and level the grounds by gently shaking.

4.Slide the funnel into the funnel rails. The brewer will read the coffee name and size ground through the chip in the funnel handle.

Image 10
Contents Post Office BOX SPRINGFIELD, Illinois Phone 217 529-6601 FAX 217BUNN-O-MATIC Commercial Product Warranty Dual Voltage Machine IntroductionVolt Machine User Notices 0 7IRE .$  #29710.0009 Ptional &IELD 7IRING0 7IRE .$  #29710.0010 Conductor for earth ground Dual Volt Toggle Switch Electrical HOOK-UPElectrical Requirements A separate conductor For earth ground Plumbing Hook UP Plumbing Requirements Tank Drain Operating Controls Viewing Assigned Recipes & Asset Number Make sure the ON/OFF switch is OFF LED will not be litInitial SET-UP Repeat for Brew B and Brew CWithout a Smart Funnel and G9-2T DBC Grinder TEA BrewingCoffee Brewing With a Smart Funnel and G9-2T DBC or MHG GrinderCleaning MediumGlossary Glossary Programming Programming SwitchesProgramming Section Ready to Brew Water Temp Programming the BrewerImportant Programming Notes Read Carefully ScreenProgramming Functions Flow Chart Programming the BrewerProcedure for setting Brew Lockout Programming Functions Level Brew LockoutProgramming the Brewer Programming Functions Level 2 Procedure for setting LanguageSET Language Procedure for setting the Units UnitsProcedure for reviewing the recipes Review Recipes Modify recipe, set up standard recipesModify Show and Next Assign Recipe Using a Smart Funnel and a G9-2T DBC or MHG Grinder Master Temp YESDONE? Card Contains Recipe for Coffee Name Setup CompleteReady to Brew Water Temp Coffee Name Show Quit SaveIf the brewing information is not correct, or it is Review RECIPES? No YESStored in the brewer’s memory Coffee Name Modify Show NextRecipe Name Modify Show Next Review Recipes No YESTEA Modify Show Next Brew OZ XX.X Done +Brew OZ Dilute Dely Done +Batches DONE? Read Dilute OZ SET Pulse Brew No YESTea recipe to be modified Water for that particular batch sizeSetting Pulse Brew Easy Pulse Brew TEA Recipes SET Pulse BrewBrew Read Dilute DelyRead Select Method Press and release YES. The display should now read Dilute OZ Press and release DONE. The display should readSelect Method Easy Next Manual 1ST on TimeSET Pulse Brew No YES OFF TimeStep Setting for the batch size just programmed. AfterOccurs for that batch size Read 2 Batches DONE?Coffee recipe to be modified NO-NAME Coffee Modify Show NextSCREEN, press and release the ON/OFF button Coffee Recipes SET Pulse Brew Last on Time Pre-Infusion to 4 minutesRead SET Pulse Brew Size to display the settings for that batch. After aDirectly to step Repeat steps 10, 11Press and release DONE. The display should read TEA Modify Show Next Pulse Brew Coffee Recipes Drip TimeRepeat steps 8 through Using -and +, adjust the brew and faucet tem- perature Master TempUsing -and +, adjust the ready temperature Procedure to set ready temperature Range 2 to 20 F 1 10 CReady Degree Procedure to Write an Ad Enable ADSProcedure to Enable/Disable Ads WriteFrom the NEW AD? screen, press and release Card Card no WriteProcedure for enabling sanitation Range 0.0 to 72.0 hrs Enabl SanitationEnableFreshTimer Enable EnergysavrProcedure to enable energy savings mode DoneCoffee Enable Fresh TimerTimer XXX RefillRefill Range 0 toProcedure to adjust the sprayhead flow rate set- ting Spray OZ/MProcedure to adjust the dilution flow rate setting Dilute OZ/MContainer READY? Quit YES Calibrate FLOW? No YESSpray Head CAL No YES Calibrate Spray Quit StartDilution CAL? No YES Calibrate FLOW? No YESSpray Head CAL No YES Container READY? Quit YESBrew C Xxxx Next Reset Brew a Xxxx Next ResetBrew B Xxxx Next Reset Brew COUNTERS? No YESTools SET Recipe TempsTemps YESEnter Asset #? Procedure to enter the asset numberAsset Number Press and release YES. The display will now readEnter Service #? Service NumberProcedure to enter the service number Service TOOLS?Test Switches Service ToolsProcedure to test components and outputs Following components can be individually tested Brew ValveP2883 36748 Test OUTPUTS? No YES Service TOOLS? No YESTest SWITCHES? No YES Right Hidden To Exit Nothing PressedDone QuencyFactory Defaults Factory Defaults No YESWill Replace ALL Brew Settings Are YOU SURE? No YES DefaultsTEA 2 Recipe Factory Default ValuesTEA 1 Recipe TEA 3 RecipeIced Coffee Recipe Factory Default ValuesHOT TEA Recipe NO-NAME Coffee RecipeTroubleshooting Probable Cause TroubleshootingProblem RemedyBrew valve Problem Probable Cause RemedyBrew switch Control BoardLong Problem Probable CauseAutomatic refill will not operate No water Tank drain clampCheck the wiring harness Automatic refill will not operate or Refill valveIf the left three digit number Water flows into tank continuously Refill valveTing To it is secureHeating Time TOO Long Connect a voltmeter across Problem is foundTank heaters Working orderMove the strainer and check for TionStrainer Direction of flow arrow must be Obstructions. Clear or replaceLime buildup Temperature probe Control Board Funnel tip 90 psi 138 and 620 kPa Brew volume adjustmentImproper water pressure Head for lime buildupFor proper extraction Brew cycle should be startedCoffee or tealeaves Water temperatureWeak beverage Type of paper filter Proper extractionSolenoids Remove and clean lime off tank heatersPlumbing lines Water supply Tank heaters Schematic Wiring Diagram ITCB-DV #%-!4#72. $!2!- I4#! I4# Schematic Wiring Diagram ITCB-C-DV