Installation Preparation

Preparation WITHOUT an Accessory Storage Drawer

PREPARE THE OPENING (cont.)

Installation over a GE/Monogram oven:

PREPARE THE OPENING (cont.)

Installation over a GE/Monogram Oven and Warming Drawer:

30

17-1/2

23-1/2

25-1/4

Construct Solid Bottom Min. 3/8Plywood Supported by 2 x 4 or 2 x 2 Runners all Four Sides

2Min.

(3Recommended)

Per Oven

Requirement

30

17-1/2

Per Warming Drawer Requirement

23-1/2

25-1/4

Construct Solid Bottom Min. 3/8Plywood Supported by 2 x 4 or 2 x 2 Runners all Four Sides

2Min.

(3Recommended)

Per Oven

Requirement

2Min.

(3Recommended)

If you are replacing a GE/Monogram electric double oven with the combined installation of an Advantium 120V and a single oven, use

the dimensions shown. The middle rail separating the two openings may need to be larger than the 2minimum shown.

NOTE: Additional clearances between the cutouts may be required. Check to be sure the oven supports above the Warming Drawer location do not obstruct the required interior depth

and height . See Warming Drawer installation instructions for details.

CAUTION:For personal safety, the mounting surface must be capable of supporting the cabinet load, in addition to the added weight of this approximate 80-pound oven, plus additional oven loads of up to 50 pounds

or a total weight of 130 pounds.

6

Image 6
Contents Installation Instructions Contents Models AvailableAdvance Planning Safety glasses or gogglesParts Supplied 8 ″Single Advantium 120 Installation Electrical RequirementsElectrical Location Single Advantium 120V Installation Prepare the OpeningInstallation over a GE/Monogram oven Installation over a GE/Monogram Oven and Warming Drawer17-1/2″ 25-1/4″ Drawer30″ 23-1/2″ ″ Min2″Min 2″Recommended 30″ 21″ 36-3/4″ Min 23-1/2″ 25-1/4″ Construct Solid 30″23-1/2″21 ″ All Four SidesWarming Drawer 21″ 25-1/4″ Cooktop Installation Instructions Slide the Oven Into the Cutout Discard plastic trim. Replace screwsInstall Bottom Trim Install Mounting ScrewsFinalize Installation Tools Required ZX2201SS-Stainless Steel for installation above 36″ onlyAllow 15″ clearance When fully open JX2200BB-Black JX2201SS-Stainless SteelRemove Packaging and Parts Assembling the Oven to DrawerAssembling the Oven to Drawer Page GE Consumer & Industrial