Chapter 4 Measurements
Insertion Loss Measurement
The transmission feed line insertion loss test verifies the signal attenuation level of the ca- ble system in reference to the specification. This test can be conducted with the Site Master in either
Required Equipment
Site Master Model S251C
Precision Open/Short, Anritsu 22N50 or Precision Open/Short/Load, Anritsu OSLN50LF
Precision Load, Anritsu SM/PL
Test Port Extension Cable, Anritsu
Optional
Device Under Test
Transmission Feed Line with Short
Procedure - Cable Loss Mode
Step 1. Press the MODE key.
Step 2. Select
Step 4. Connect the Test Port Extension cable to the RF Out port and calibrate the Site Master as described on page
Step 5. Save the calibration set up (page
Step 6. Connect the Device Under Test to the Site Master phase stable Test Port Exten- sion cable. A trace will be displayed on the screen as long as the Site Master is in sweep mode.
Step 7. Press the AMPLITUDE key and set the TOP and BOTTOM values of the dis- play. In the example below, the TOP is set to 2, and the BOTTOM is set to 5.
Step 8.
Step 9.
Step 10.
Step 11.
Step 12.
Step 13.
Press the MARKER key.
Set M1 to MARKER TO PEAK.
Set M2 to MARKER TO VALLEY.
Calculate the measured insertion loss by averaging M1 (marker to peak) and M2 (marker to valley) as follows:
Insertion Loss M1 M2
2
Press SAVE DISPLAY (page