Operation – Battery Replacement

UPS / XR

Install the Battery Modules in the lowest available bay (4 across in 523mm UPS versions, 2 across in 352mm UPS versions).

Position the Battery Unit to slide in between the grooves and push completely into the UPS to ensure connection.

NOTE!

If a problem is reported, ensure that the modules in question are correctly installed. If the problem persists, refer to the Troubleshooting section of this guide.

NOTE!

Allow for a 24-hour recharging period of the batteries after system start-up / battery replacement for battery monitoring data to become fully reliable.

990-2359A Smart-UPS® VT 10-30kVA, 200/208V and XR Battery Enclosure Operation Guide

31

Page 39
Image 39
American Power Conversion 200/208 V, 10-30 KVA manual  