3. Slightly open the top coil vent.
4. At the water supply, open the appropriate valves to begin letting water slowly enter the equipment.
5. At the equipment, close the top coil vent when water begins slowly flowing out of the vent.
6. At the water supply: |
| |
a. Open all valves (no greater | na1768a | |
than 76 l/m [20 gpm]), | ||
| ||
allowing the water supply to |
| |
reach the highest possible flow |
| |
to the equipment for 45 seconds. |
|
b.Close the valves to a
c.Open the valves to maximum flow for another 45 seconds.
d.Balance the system to provide the designed flow rate to all equipment.
Top coil vent
InRow RC Installation | 21 |