3. Slightly open the top coil vent.

4. At the water supply, open the appropriate valves to begin letting water slowly enter the equipment.

5. At the equipment, close the top coil vent when water begins slowly flowing out of the vent.

6. At the water supply:

 

a. Open all valves (no greater

na1768a

than 76 l/m [20 gpm]),

 

allowing the water supply to

 

reach the highest possible flow

 

to the equipment for 45 seconds.

 

b.Close the valves to a 3.8–11.4 l/m (1–3 GPM) flow for 60 seconds.

c.Open the valves to maximum flow for another 45 seconds.

d.Balance the system to provide the designed flow rate to all equipment.

Top coil vent

InRow RC Installation

21

Page 27
Image 27
APC ACRC100, ACRC103 manual Than 76 l/m 20 gpm