APC ACRC103, ACRC100 manual Mechanical Connections, Piping

Models: ACRC100 ACRC103

1 36
Download 36 pages 32.09 Kb
Page 22
Image 22

Mechanical Connections

Piping

Note: Ensure coolant water quality complies with guidelines set forth in IB0125GB001.

Water. Install shutoff valves for routine service and emergency isolation of the equipment. When a CDU is not used, you must install circuit setters to regulate the chilled water flow for each InRow RC air conditioner. See “Piping Diagrams,” beginning on page 8.

Layout and piping considerations.

Fluid pipes are not allowed directly above electrical equipment. All piping must be installed above the aisles as shown. If any piping makes a turn, or must be routed over electrical equipment, there must be a drip tray under the pipe that will protect the equipment from condensation and leaks. All piping must be kept separate from any electrical runs or wiring.

Hot Aisle Containment

CDU

Top piping examples shown

 

NetShelter NetShelter NetShelter

UPS

PDU

NetShelter RC NetShelter NetShelter RC NetShelter

InRow

PDU

UPS NetShelter RC NetShelter NetShelter RC NetShelter

CDU

NetShelter NetShelter RC NetShelter NetShelter RC NetShelter NetShelter

na1941a

Insulation. Insulate water lines to protect

personnel and to minimize condensation.

Note: Using either tape or glue, completely seal the insulation boots covering the unused supply and return connections.

16

InRow RC Installation

Page 22
Image 22
APC ACRC103, ACRC100 manual Mechanical Connections, Piping