CHAPTER 4: INSTALLATION
27
Connecting Load Equipment to the UPS
1. Plug all load equipment into PDU receptacles .
2. Ensure that all PDU circuit breakers are turned
ON. Refer to Table 2 on page 8 for additional
information.
SYPD3 (200/208/240 V)
SYPD4 (220/230/240 V)