START-UP CHECKLIST
MODEL NO.: |
| SERIAL NO.: |
DATE:TECHNICIAN:
I. PRE-START-UP
VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT VERIFY INSTALLATION OF INDOOR FAN MOTOR ADJUSTMENT BOLT AND PLATE VERIFY INSTALLATION OF
VERIFY INSTALLATION OF FLUE HOOD AND WIND BAFFLE
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTRUCTIONS
VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT
CHECK GAS PIPING FOR LEAKS
CHECK THAT FILTERS AND SCREENS ARE CLEAN AND IN PLACE
VERIFY THAT UNIT IS LEVEL
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE, AND VERIFY SETSCREW IS TIGHT
VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED VERIFY THAT SCROLL COMPRESSOR IS ROTATING IN THE CORRECT DIRECTION
VERIFY THAT CRANKCASE HEATER HAS BEEN ENERGIZED FOR 24 HOURS
II.START-UP ELECTRICAL
SUPPLY VOLTAGE |
|
|
|
| ||||||
COMPRESSOR AMPS — COMPRESSOR NO. 1 | L1 |
|
| L2 |
|
| L3 |
|
| |
— COMPRESSOR NO. 2 | L1 |
|
| L2 |
|
| L3 |
|
|
SUPPLY FAN AMPS |
|
| EXHAUST FAN AMPS |
|
| |||
TEMPERATURES |
|
|
|
|
|
|
| |
|
| F DB |
|
|
| |||
|
| F DB |
| F WB | ||||
COOLING SUPPLY AIR |
|
| F |
|
|
| ||
GAS HEAT SUPPLY AIR |
|
| F |
|
|
|
PRESSURES |
|
|
|
|
|
|
GAS INLET PRESSURE |
|
| IN. WG |
|
|
|
GAS MANIFOLD PRESSURE | STAGE NO. 1 |
| IN. WG | STAGE NO. 2 |
| IN. WG |
REFRIGERANT SUCTION | CIRCUIT NO. 1 |
| PSIG | CIRCUIT NO. 2 |
| PSIG |
REFRIGERANT DISCHARGE | CIRCUIT NO. 1 |
| PSIG | CIRCUIT NO. 2 |
| PSIG |
VERIFY REFRIGERANT CHARGE USING CHARGING CHART ON PAGE 37.
GENERAL
ECONOMI$ERIV MINIMUM VENT AND CHANGEOVER SETTINGS TO JOB REQUIREMENTS
CUT ALONG DOTTED LINE
CUT ALONG DOTTED LINE
Copyright 2006 Bryant Heating & Cooling Systems | Printed in U.S.A. | CATALOG NO. |