II.HEATING SECTION START-UP AND ADJUSTMENTS
CAUTION: Complete the required procedures given in the
Do not jumper any safety devices when operating the unit.
Ensure that burner ori®ces are properly aligned. Unstable operation may occur when the burner ori®ces in the mani- fold are misaligned.
Follow the lighting instructions on the heating section opera- tion label (located inside the burner access door) to start the heating section.
When lighting the unit for the ®rst time, perform the follow- ing additional steps: If the gas supply pipe was not purged before connecting the unit, it will be full of air. It is recom- mended that the ground joint union be loosened and the supply line be allowed to purge until the odor of gas is de- tected. Never purge gas lines into a combustion chamber. Im- mediately upon detection of gas odor, retighten the union. Allow 5 minutes to elapse, then light unit in accordance with Check- ing Heating Control Operation section below.
A. Checking Heating Control Operation
Start and check the unit for proper heating control operation as follows: (Also see unit lighting instructions located inside the burner access panel.)
1.Turn on unit electrical supply and manual gas valve.
2.Set system switch selector at HEAT position and fan switch at AUTO. or ON position. Set heating temperature lever above room temperature.
3.The
4.After a call for heating, the main burners should light within 5 seconds. If the burner does not light, then there is a
5.The
6.The
7.Adjust air¯ow to obtain a temperature rise within the range speci®ed on the unit nameplate.
NOTE: The default value for the
If the limit switch trips at the start of the heating cycle dur- ing the evaporator ON delay, the time period of the ON delay for the next cycle will be 5 seconds less than the time at which the switch tripped.
EXAMPLE: If the limit switch trips at 30 seconds, the
To prevent
The
To restore the original default value, reset the power to the unit.
To shut off unit set system switch selector at OFF position. Resetting heating selector lever below room temperature will temporarily shut unit off until space temperature falls below thermostat setting.
B. Safety Relief
A soft solder joint at the suction service Schrader port pro- vides pressure relief under abnormal temperature and pres- sure conditions.
C. Ventilation (Continuous Fan)
Set fan and system switch selectors at ON and OFF posi- tions, respectively. Evaporator fan operates continuously to provide constant air circulation. When the
D. Gas Input
Check gas input and manifold pressure after unit
CAUTION: These units are designed to consume the rated gas inputs using the ®xed ori®ces at speci- ®ed manifold pressures as shown in Table 5. DO NOT REDRILL THE ORIFICES UNDER ANY CIRCUMSTANCES.
The rated gas inputs shown in Table 5 are for altitudes from sea level up to 2000 ft above sea level. These inputs are based on natural gas with a heating value of 1050 Btu/ft3 at
0.65speci®c gravity, or LP gas with a heating value of
2500 Btu/ft3 at 1.5 speci®c gravity. For elevations above 2000 ft, reduce input 4% for each 1000 ft above sea level. When the gas supply being used has a different heating value or speci®c gravity, refer to national and local codes, or contact your distributor or branch to determine the required ori®ce size. Refer to Table 6 for the correct ori®ce to use at high al- titudes. Kits are available from your distributor.
E. Adjusting Gas Input
The gas input to the unit is determined by measuring the gas ¯ow at the meter or by measuring the manifold pressure. Measuring the gas ¯ow at the meter is recommended for natu- ral gas units. The manifold pressure must be measured to determine the input of propane gas units.
Measuring Gas Flow at Meter Method Ð Natural Gas Units
Minor adjustment can be made by changing the manifold pres- sure. The manifold pressure must be maintained between 3.2 and 3.8 in. wg on
NOTE: All other appliances that use the same meter must be turned off when gas ¯ow is measured at the meter.
Proceed as follows:
1.Turn off gas supply to unit.
2.Remove pipe plug on outlet of gas valve or manifold, then connect manometer at this point. Turn on gas to unit.
Ð18Ð