Power up and test

Ensure the mains plug is fitted with a 3A fuse.

Switch on

Power up the system by inserting the mains plug.

Wait approximately 30 seconds for the system power up routine to be complete.

Check that the vital activity LED is flashing. This is the top led of the four LEDs in the CCU MDF area.

Check the Power led is lighting. This is the third led in the CCU MDF area

Commissioning

1.Remove any anti-scratch protective film from Featurephone LCD’s.

2.Label up all Featurephones and other telephones.

3.Ensure that all Featurephones provide dialling tone, ringing and hands free (loud speaking) facilities. Check that the display is not showing corrupt information.

4.Carry out a 'First Day Reset'.

5.Check that all other telephones are connected. Make sure all these phones ring and that you can dial from them.

6.Commission System