48TJD008-014 48TJE008-014 48TJF008-012
Single-Package Rooftop Heating/Cooling Units
Installation, Start-Up and
Service Instructions
CONTENTS
Page
SAFETY CONSIDERATIONS . . . . . . . . . . . . . . . . . . . 1
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Step 1 Ð Provide Unit Support . . . . . . . . . . . . . . . 1
·ROOF CURB
·SLAB MOUNT
Step 2 Ð Field Fabricate Ductwork . . . . . . . . . . . . 2
Step 3 Ð Install External Trap for Condensate Drain . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Step 4 Ð Rig and Place Unit . . . . . . . . . . . . . . . . . . 2
· POSITIONING
Step 5 Ð Install Flue Hood . . . . . . . . . . . . . . . . . . . 8 Step 6 Ð Install Gas Piping . . . . . . . . . . . . . . . . . . . 8 Step 7 Ð Make Electrical Connections . . . . . . . . 8
·FIELD POWER SUPPLY
·FIELD CONTROL WIRING
·HEAT ANTICIPATOR SETTINGS
Step 8 Ð Adjust Factory-Installed Options . . . 11
·APOLLO CONTROL
·MANUAL
·OPTIONAL DURABLADE ECONOMIZER
·OPTIONAL PARABLADE ECONOMIZER
Step 9 Ð Adjust Evaporator-Fan Speed . . . . . . 16
SAFETY CONSIDERATIONS
Installation and servicing of
Untrained personnel can perform basic maintenance func- tions of cleaning coils and ®lters and replacing ®lters. All other operations should be performed by trained service per- sonnel. When working on
Follow all safety codes. Wear safety glasses and work gloves. Use quenching cloth for unbrazing operations. Have ®re ex- tinguishers available for all brazing operations.
Disconnect gas piping from unit when leak testing at pressure greater than 1¤2 psig. Pres- sures greater than 1¤2 psig will cause gas valve damage resulting in hazardous con- dition. If gas valve is subjected to pres- sure greater than 1¤2 psig, it must be replaced before use. When pressure testing ®eld- supplied gas piping at pressures of 1¤2 psig or less, a unit connected to such piping must be isolated by manually closing the gas valve(s).
Before performing service or maintenance operations on unit, turn off main power switch to unit. Electrical shock could cause personal injury.
INSTALLATION
Unit is shipped in the vertical discharge con®guration. To convert to horizontal con®guration, remove screws from side duct opening covers and remove covers. Using the same screws, install covers on vertical duct openings with the insulation- side down. Seals around duct openings must be tight. See Fig. 1.
Step 1 Ð Provide Unit Support
ROOF CURB Ð Assemble and install accessory roof curb in accordance with instructions shipped with curb. See Fig. 2. Install insulation, cant strips, roo®ng felt, and counter ¯ashing as shown. Ductwork must be attached to curb. If gas is to be routed through the curb, attach the accessory
IMPORTANT: The gasketing of the unit to the roof curb is critical for a watertight seal. Install gasket sup- plied with the roof curb as shown in Fig. 2. Improp- erly applied gasket can also result in air leaks and poor unit performance.
Curb should be level. Unit leveling tolerances are shown in Fig. 3. This is necessary for unit drain to function prop- erly. Refer to Accessory Roof Curb Installation Instructions for additional information as required.
Manufacturer reserves the right to discontinue, or change at any time, speci®cations or designs without notice and without incurring obligations.
Book | 1 | 4 |
| PC 111 | Catalog No. | Printed in U.S.A. | Form | Pg 1 | Replaces: | |
Tab | 1a | 6a |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|