SYSTEM RACK
Shelf Number | Switch 1, Open Sections |
1 | ALL Closed |
2 | 1 |
3 | 2 |
4 | 1,2 |
5 | 3 |
6 | 1,3 |
7 | 2,3 |
8 | 1,2,3 |
9 | 4 |
10 | 1,4 |
11 | 2,4 |
12 | 1,2,4 |
13 | 3,4 |
14 | 1,3,4 |
15 | 2,3,4 |
16 | 1,2,3,4 |
17 | 5 |
18 | 1,5 |
Verify switch settings of S1 in Table
Verify the backplane switch settings for S2 - S8 on each shelf are set with all sections closed.
PTM Switch SettingsVerify the switch settings of the Power Termination Module (PTM) are as follows:
S5, S7 all sections closed; S6, S8 section 8 closed;
sections 1, 2, 3, 4, 5, 6, 7 open
Call Processor Connection To SwitchVerify the Call Processor connection to the System rack as follows:
1.NetIDB Connection: Use the 20’
2.NetCSB Connection: Use the 20’
3.Install a Power Termination Module in the first slot on the left side of each shelf.
4.Install the NetNIM in Shelf 1, Slot 0.
5.Turn "On" both Power Supplies, turn "On" the Call Processor and note that the four LEDs on each PTM card are "On".
a.Verify that the Call Processor comes up in the Switch mode.
b.Verify that the Call Processor displays the Net- NIM’s clock status, "A Pass B Pass" in the Call Processor’s Device Activity window. If neces- sary, press the reset button S1on the NetNim to activate the clock status.)
PCM Bank VerificationPCM Bank Verification requires two Channel Interface Modules (CIMs).
1.On both CIMs place a patch cord from the top jack of J1 to the top jack of J2 (see Figure
2.Close S1, sections
3.On both CIMs set switch sections as follows:
Switch SectionS3
S4
S5
4.Set one module for System Test "5"
5.Set the second module for System Test "6".
6.Loop Primary Tx PCM to the Primary Rx PCM by connecting a cable