SYSTEM RACK
Shelf S1 Switch Settings
Verify switch settings of S1 in Table
Shelf Number | Switch 1, Open Sections |
|
|
1 | ALL Closed |
2 | 1 |
3 | 2 |
4 | 1,2 |
5 | 3 |
6 | 1,3 |
7 | 2,3 |
8 | 1,2,3 |
9 | 4 |
10 | 1,4 |
11 | 2,4 |
12 | 1,2,4 |
13 | 3,4 |
14 | 1,3,4 |
15 | 2,3,4 |
16 | 1,2,3,4 |
17 | 5 |
18 | 1,5 |
19 | 2,5 |
20 | 1,2,5 |
21 | 3,5 |
22 | 1,3,5 |
23 | 2,3,5 |
24 | 1,2,3,5 |
|
|
Backplane Switch Settings
Verify the backplane switch settings for S2 - S8 on each shelf are set as follows:
Shelf
Sections 1,2,7 open
PTM Switch Settings
Verify the switch settings of the Power Termination Module (PTM) are as follows:
S5, S7 Sections 3,4,5,6,7 closed;
Sections 1,2 open
S6, S8 Sections 2,3,6 closed;
Sections 1,4,5,7,8 open
Call Processor Connection To Switch
Verify the Call Processor connection to the System rack as follows:
1.NetIDB Connection: Use the 20’
2.NetCSB Connection: Use the 20’
3.Install a Power Termination Module in the first slot on the left side of each shelf.
4.Install the NetNIM in
5.Turn "On" both Power Supplies, turn "On" the Call Processor and note that the four LEDs on each PTM card are "On".
a.Verify that the Call Processor comes up in the Switch mode.
b.Verify that the Call Processor displays the Net- NIM’s clock status, “A Pass B Pass” in the Call Processor’s Device Activity window. (If neces- sary, press the reset button S1on the NetNIM to activate the clock status.)
PCM Bank Verification
PCM Bank Verification requires
1.On both CIMs place a patch cord from the top jack of J1 to the top jack of J2 (see Figure
2.On both CIMs
Close S1, Sections
3.On both CIMs set switch sections as follows:
Switch Section
S3
S4
S5