Site Considerations

Floor Load

The weight and footprint size for your machine is located in the machine data sheet. Some residen- tial floors may require additional reinforcement to support the machine, workpieces, and operator.

Working Clearances

Consider existing and anticipated needs, size of material to be processed through each machine, and space for auxiliary stands, work tables or other machinery when establishing a location for your new machine. See Figure 3 for the minimum working clearances.

24"

35"

Figure 3. Model G0458 Working clearances.

Unsupervised children and visitors inside your shop could cause serious per- sonal injury to themselves. Lock all entrances to the shop when you are away and DO NOT allow unsupervised children or visitors in your shop at any time!

Stand

 

Components and Hardware Needed:

Qty

Carriage Bolts M8-1.25 x 15

16

Serrated Flange Nuts 12mm

16

Top Short Brackets

2

Bottom Short Brackets

2

Stand Legs

4

Top Long Brackets

2

Bottom Long Brackets

2

We recommend assembling the stand upside down. To make it easier, have an assistant hold the pieces while you assemble the stand.

NOTICE Do not final tighten stand bolts until the stand components have been assembled.

To assemble the stand:

1.Mount a top and bottom long bracket to a stand leg and loosely secure with two M8- 1.25 x 15 carriage bolts and serrated flange nuts as shown in Figure 4.

Leg

Bottom Long Bracket

Top long bracket

Figure 4. Top and bottom long brackets secured

to a stand leg.

-12-

G0458 18" Open End Belt/Drum Sander

Page 14
Image 14
Grizzly G0458 instruction manual Site Considerations, Stand, Components and Hardware Needed Qty, To assemble the stand