10" (25.4 cm)

INTERIOR

WALL SHIELD

12" (30.5 cm)

Figure 18. Flue Pipe & Firestop

For Vertical Runs - One firestop is REQUIRED at the hole in each ceiling through which the flue passes.

To install firestops for vertical runs that pass through ceilings:

Position a plumb bob directly over the center of the verti- cal flue component.

Mark the ceiling to establish the center point of the flue.

Drill a hole or drive a nail through this center point.

Check the floor above for any obstructions, such as wir- ing or plumbing runs.

Reposition the heater and flue system, if necessary, to accommodate the ceiling joists and/or obstructions.

Cut a 25.4 cm X 30.5 cm hole through the ceiling, using the firestop pipe opening as a guide.

Frame the hole with framing lumber the same size as the ceiling joists.

10" (25.4 cm)

10” (25.4 cm)

 

 

CHIMNEY

 

HOLE

NEW

EXISTING CEILING

JOISTS

FRAMING

 

MEMBERS

 

CEILING

 

Figure 19. Hole and New Framing Members

Heat & Glo • 6000TRS-CE2049-900 Rev. Q • 2/11