5Allow 45 seconds for the unit to fully boot. The LINK LED will be lit if there is a valid network connection. The ACT LED gives information about what the MPS is doing; for example, when code is being downloaded as the unit boots, the LED will blink green quickly. If you have connected a 100BASE-T cable (MPS100 only), The Link and 100MBit LEDs should both be solid green. If not, check your network con- nection.

6Print a Test page by pressing the Test/Reset button.

Note: If the Power LED does not light or the Test page does not print, refer to Appendix B.