Lochinvar SCH-I-O Collector Installation continued, SCH parallel mounting instructions

Models: SCH-I-O

1 44
Download 44 pages 4.32 Kb
Page 29
Image 29
4 Collector Installation (continued)

SCH Collectors Installation & Operation Manual

4 Collector Installation (continued)

SCH parallel mounting instructions

1.Install roof attachments (see the Roof Attachment Section on pages 13 - 27 of this manual).

2.Install the horizontal bar(s) (FIG.'s 4-2A and 4-2B) using the square disk, hex bolt, and washers provided in the kit.

Figure 4-2AInstall Horizontal Bars

ENDS OF HORIZONTAL BARS

MUST BE PARALLEL TO ENSURE

PROPER COLLECTOR

ORIENTATION

4.Ensure lifting rings are installed and properly spaced as per FIG. 4-4.

Figure 4-4Lifting Rings

SCH parallel mounting instructions< 30° < 30°

6.5 ft.

6.5 ft.

< 30°Figure 4-2AInstall Horizontal Bars < 30°

6.5 ft.

8.5 ft.

Figure 4-2B Spacing

aa

x

a

=

 

 

=

 

a = 2 - 10 in.

=

a

 

 

x

 

 

55 - 63 in.

 

5.Position the collector onto the substructure and hanger brackets (FIG. 4-5).

￿WARNING Only loosen the crane connection when the collectors are completely fixed to the

substructure.

Figure 4-5Position Collector On Substructure

POSITION PANEL ONTO

SUBSTRUCTURE

3.Install the Z-hooks per FIG. 4-3 using the specified number of brackets.

Figure 4-3Install Z-Hooks

SCH065 SCH090, 110, AND 130

2 x / per collector

3 x / per collector

Figure 4-4Lifting Rings Z-HOOK

6.Secure the collector to the Z-hook(s) using the square disk and hex bolt provided in the kit (FIG. 4-6).

Figure 4-2B Spacing 29

INSTALL Z-HOOKS

Page 29
Image 29
Lochinvar SCH-I-O Collector Installation continued, SCH parallel mounting instructions, 2A Install Horizontal Bars