9.3.6.Assembly knowhow of the Body

9.3.6.1.Setting LCD

The order of tightening screw (DXQT26+D5FNL) : a b

LCD unit

Screw b

Screw a

The hinge is drawn up and the screw is tightened.

9.3.6.2. Line processing LCD Cable (bottom case side)

Standard

Conductive cloth

Connection order Inverter cable

LCD cable

The work order

Safety Work

Processes that cable should not run aground on the DC- jack holder.

Sheet’s edge and edge are matched and put. (The inclination part is pressurized. )

Safety Work

Cable is processed under the point hanging part. (Floatage prevention)

Safety Work

Cable is processed to the DC-jack holder. Safety Work

Cable is processed to the ditch.

Put the conductive cloth It is not possible to

recycle when flaking off.

Sheet

VGA connector

Safety Work

Processes so that sheet should not run aground in the screw

hole land.

(The figure below is state after wiring)

 

 

 

 

Safety Work

 

Cable

 

Sheet must not

 

 

 

 

roll the holder.

 

 

 

 

Screw hole land

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Safety Work

Main board

The space is secured.

Bottom case

73

Page 73
Image 73
Matsushita CF-W5LWEZZ1 2 Assembly knowhow of the Body, Setting LCD, Line processing LCD Cable bottom case side