3.PRE-INSTALLATION EQUIPMENT VERIFICATION

3.PRE-INSTALLATION EQUIPMENT VERIFICATION

A.GENERAL

(1)Ensure the available voltage and phase correspond with humidifier voltage and phase as indicated on the humidifier’s specification label.

(2)Ensure that the external fuse disconnect is sufficient size to handle the rated amperage as indicated on the humidifier’s specifications label. Refer to local building codes.

(3)Report any discrepancy immediately to the site engineer.

(4)Location and mounting is described in Chapter 10-10.

(5)For typical installation see Figures 6 & 7.

10-00

Page 9 2008-10-01