Complying with NEBS

2. Installation

Complying with NEBS

The following must be taken into consideration for compliance with Network

Equipment-Building System (NEBS) requirements.

Connection to the CO Ground Lug

Connection to the CO Ground Lug Procedure

To connect to the CO ground lug:

1.Strip back the insulation approximately 1/4- to 3/8-inch (6.5 to 9.5 mm) on the 14 AWG copper ground wire.

2.Loosen the screw on the GND lug located on the rear surface at the center of the bottom edge.

3.Insert the stripped end of the wire into the open end of the GND lug and tighten the lug’s screw. Make sure it makes contact with the stripped portion of the wire.

ESD Wrist Strap Jack

A noninsulated banana jack is located at the left front of the Hotwire 8620

GranDSLAM to provide a ground for an ESD wrist strap.

HANDLING PRECAUTIONS FOR

!STATIC-SENSITIVE DEVICES

This product is designed to protect sensitive components from damage due to electrostatic discharge (ESD) during normal operation. When performing installation procedures, however, take proper static control precautions to prevent damage to equipment. If you are not sure of the proper static control precautions, contact your nearest sales or service representative.

2-8

July 2003

8620-A2-GN20-40