2. Installation
Verifying the Installation
To verify the hardware installation, observe the front panel indicators.
ALARMS
|
| M | M | |
DC |
| A | I | |
F | J | N | ||
POWER | ||||
A | O | O | ||
| ||||
A B N | R | R |
ESD | SYSTEM | ATM | BUS | DSL | PORT |
|
|
| IP | MVL | 8314 |
|
|
|
|
|
| 3 | |||||||
| SYSTEM | ATM | BUS | DSL | PORT |
|
|
| IP | MVL | 8314 | 2 |
|
|
|
|
|
|
|
|
|
| |||
|
|
|
|
|
|
|
|
| MCP |
| 8000 | 1 |
GranDSLAM 8620 |
|
|
|
|
|
| TX | RX | 10/100BT | 8025 | A | |
DC FUSES | RTN | ALARMS | ALARM | CLOCK | SERIAL | LAN | SIM |
| ||||
|
| DC |
|
|
|
|
| SIM | ||||
|
| POWER |
|
|
|
|
|
|
| |||
|
|
|
|
|
|
|
|
|
|
|
| AC INPUT |
|
|
|
|
|
|
|
|
|
|
|
|
In normal operation:
νThe PWR A and/or PWR B LEDs on the front panel must be in the ON state (green):
—If you are using a single 48 VDC power source, then only the green PWR A LED will be ON.
—If you are using dual 48 VDC power sources, then both the green PWR A and PWR B LEDs will be ON.
—If you are using a single AC power source, then the green PWR A LED must be ON.
—If you are using both an AC power source and a 48 VDC power source, then both the PWR A and PWR B LEDs must be ON.
νThe yellow FAN ALM LED on the front panel must be OFF.
νIf you installed an SCP card, verify that the SYSTEM ACTIVE LED is cycling off and on.
νIf you installed an MCP card, verify that the SYSTEM OK LED is cycling off and on.
νVerify that the SYSTEM OK LED on any DSL cards is cycling off and on.
If these LEDs fail to appear as described, see Troubleshooting Table and LEDs in Chapter 4, Troubleshooting, for more information.
| July 2003 |