Site Preparation

The following steps must be completed before installing the system hardware. If the steps are not already completed refer to each individual section for details.

†MCU location prepared. Typically the MCU is installed in the telephone equipment room. This location must have sufficient backboard space or rack space, and -48 volt power available.

†The correct number of cross-connect blocks (or equivalent) are installed and connected to a 25-pair Telco wire terminated with an RJ-21 male connector at the MCU location. The number of blocks required depends on the number and type of Interface Modules installed. Refer to Chapter 4, section Prepare Demarc Blocks for more information.

†A two-pair cable to each Base Station as designated on the building floor plans.

†The Base Station wiring is terminated with RJ-45 crimp-on plugs at the designated Base Station locations. Refer to Chapter 4, section Terminate Cables at Base Station Locations for more information.

†The Base Station wire is terminated at the appropriate cross- connect demarc blocks. Refer to Chapter 4, section Connect Cables from Base Stations and Phone Lines to Demarc Blocks.

†The analog or digital phone extensions from the phone system are terminated at the appropriate cross-connect demarc block and the block is labeled. Refer to Chapter 4, section Connect Cables from Base Stations and Phone Lines to Demarc Blocks.

†A dedicated dial line is available with an RJ-11 jack for the diagnostic modem.

†An IBM-compatible PC is available to serve as the Operator’s Console for system administration.

†A system administrator is designated for the SpectraLink system. This person should be present for the installation. The Polycom field service engineer will provide system training to the system administrator on the day following the installation.