SpectraLink 6300 MCU: Facility Preparation

4.When properly attached the Base Station should sit almost flush against the ceiling and be tightly attached to the clip and T-bar grid work.

5.Once the Base Station is anchored to the fastener, lift the acoustical tile and plug the RJ-45 8-pin modular plug into the connector on the top of the Base Station.

The LED will blink red and green as the system software downloads to the Base Station and the Base Station is tested.

When the LED blinks amber, the system is ready for operation.

When the LED blinks green, a handset has established a radio link with that Base Station.

If the LED turns solid red or other red/green sequence, refer to SpectraLink 6300 MCU Maintenance and Diagnostics.

Mount Base Stations on Finished Ceilings

If this site does not have a dropped tile ceiling, the Base Station can be mounted to a finished ceiling or wall with a 4 to 5” long 1/4” -20 TPI plastic or nylon screw or bolt (such as a lag screw).

The customer’s wire contractor is responsible for this installation.

1.Drill two holes approximately 1” apart. Make the holes large enough to accommodate the RJ-45 connector and a bolt to secure the Base Station.

2.Insert a wide washer above the ceiling, then screw the bolt into the beam or ceiling.

3.Insert three nuts on the bolt, then screw the Base Station into the bolt, being careful not to insert the bolt more than 1/3”, five full turns, into the Base Station.

If the ceiling is open with I-beams or pipe construction, mount the

Base Station with I-beam clamps or pipe clamps.