SpectraLink 6300 MCU: Facility Preparation

unlimited access to the Customer Support Hotline for additional assistance.

Union labor

In some areas strict labor union rules will preclude the Polycom representative’s ability to install the equipment without union assistance. If such rules are in force in the local area, the customer must ensure that sufficient union help is available at the scheduled installation time to carry out the following functions:

Install Base Stations

Move and reinstall Base Stations

Make cabling changes at cross-connect blocks

Run cables

Make and modify electrical connections

Prepare Location for Shelves

Polycom recommends an operational temperature range of 0º

40º C (31º–104ºF). Optimal temperature is 20º C (68º F). Humidity recommendation is 20%– 80% (non-condensing).

The MCU, composed of up to 20 shelves and one Intershelf Junction Panel, is usually installed in or near the telephone equipment room. If this is not possible, the MCU can be located anywhere that the telephone system lines are accessible.

The number and arrangement of the system shelves depends on the size and configuration of the system.

System Controller

Shelves

Base Stations

Users

Part Number

Supported

Supported

Supported

CSC301/ CSO301

1

60

160

CSC306/ CSO306

6

360

960

CSC320/ CSO320

20

1,000

3,200

 

 

 

 

Consideration should be given to:

Environmental conditions. The system outputs 28 BTUs per hour, per interface module.

Space for the backboard or rack.

22

PN: 1725-36122-001_M.doc

Page 22
Image 22