UPS Power Management

6.To turn off the UPS and have it stay off (requiring local interaction to turn it back on), change Load Segment to Restart following the return of AC Line to NO.

If you want to effectively reboot the UPS and the associated load, then set Load Segment to Restart following the return of AC Line to YES and set Delay Before Segment Restart to a valid delay value to allow the UPS to restart after the specified delay.

7.After choosing the desired values, select Set Values to update the card with the new information.

8.Select Control from the ConnectUPS Web/SNMP Card menu at the top of the home page and select Load Segment “ALL” or the appropriate load segment

“NUMBER(S)”. Then select Turn UPS Off.

9.To initiate the shutdown sequence, select Set Values which instructs the ConnectUPS Web/SNMP Card to send the appropriate information to the UPS and any clients running the NetWatch client software.

Planning a Scheduled UPS Shutdown and Restart

You may use the ConnectUPS Web/SNMP Card to schedule the day of the week and time of a shutdown and a startup. The ability to schedule shutdowns and startups is UPS dependent (consult your UPS documentation for more information).

1.Select Configuration from the menu at the top of the home page, then UPS Shutdown Schedule.

2.Login as a Superuser.

3.You may configure up to seven event pairs. Enter the upcoming Shutdown Day and Shutdown Time, and if needed, the Restart Day and Restart Time. Times are in 24-hour format based on the date and time set within the ConnectUPS Web/SNMP Card.

4.Click Set Values to update the card.

5.Once the values are set, select Control from the menu at the top of the home page.

24

ConnectUPSZ Web/SNMP Card (X and BD Models) User’s Guide : Rev A www.powerware.com