accident.

3. Do not open the case to disassemble and reconstruct the product.

It may cause electric shock, operation failure and disaster such as fire. In addition, note the product, which is disassembled or reconstructed, may not satisfy the functions and performance in the specifications and is out of guarantee.

4.Do not operate the product with the wet hands. It may cause electric shock or accident.

!WARNING

1.Do not drop, hit to the object and give excessive impact (10G or more) at handling.

Though Ionizer itself doesn’t break, inside construction might be broken and cause malfunction.

2.When cable is mounted or eliminated, pinch modular plug claw with finger and insert or take out the plug itself vertically. If mounted or eliminated to inappropriate direction, mounting part of modular jack might be damaged and finally it leads to operation failure.

2. Installation

2-1. Installation of Ionizer body

Investigate the places where static problem occurs, or process and parts which generate ESD (Electro static discharge), and carefully consider the required conditions to ensure appropriate static charge elimination before installation.

1.Installation height

When the ionizer is installed, keep the distance between charged objects and the ionizer within the

range below.

Ion-production

Distance between the charged objects and ionizer (mm)

frequency

 

 

With air purge (note)

W/o air purge

Hz

 

 

1

400 to 2000

400 to 500

3

300 to 2000

300 to 400

5

300 to 2000

300 to 400

10

200 to 2000

200 to 300

15

200 to 2000

200 to 300

20

150 to 2000

150 to 250

30

50 to 2000

50 to 200

60

50 to 2000

50 to 150

(Note)As the installation height stated above is a standard, check the effect of the static charge elimination before installation.

The minimum installation height should be 200mm or more when the feed back sensor is use, and that for the auto balance sensor should be 100mm or more. When the ionizer is used outside of these conditions, be sure to check if these sensors will operate properly.

2.Mount end brackets on both sides of the ionizer body with the attached M4 threads.

Attached M4 threads