Three cable knockout plates are provided at bottom of each 100/125/150/180/225kVA UPS. Holes are recommended in Figure 11.3.

The installing electrical contractor must punch the 5 holes.

0.8”

Plate #1

Plate #2

Plate #3

4” Dia.

2” Dia.

0.4”

AC Input

Bypass

AC Output

Battery

Control

 

 

 

 

Wires

Three solid rectangles show the cable knockout plates’ outline. The dashed rectangle shows the UPS opening under the plates.

Figure 11.3 - Cable knockout plates at the bottom (100~225kVA).

The terminal busses are shown in Figure 11.4. The busses are located inside of the 250/300kVA UPS at the top. The dashed line shows the side view of the screw holes. The screws are used to tighten the lugs.

External cable size recommendations are located in Table 11.6 and 11.7. These tables show only the torque to tighten a terminal bus & a corresponding lug. Torque to tighten the cable end in a compression lug shall be specified by the lug vendor recommended in Table 11.8.

1

 

2

 

3

 

4

 

5

 

6

 

7

 

8

 

9

 

 

10

 

11

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

U V W

-

+

 

U V W

N

U V W

 

 

 

 

 

 

 

AC INPUT

BATTERY

BYPASS INPUT

 

AC OUTPUT

3-phase 3-wire

 

 

 

3-phase 4-wire

 

3-phase 4-wire

Figure 11.4 - Terminal Busses of the 250/300kVA UPS.

31

Page 32
Image 32
Toshiba G8000 Series installation manual Phase 3-wire Phase 4-wire