| Step 5: Cable Drum Installation |
|
| |||||
|
|
|
|
|
| HEAD CAP SCREW | ||
| NOTE: Do not remove shrink wrap from cable |
|
| DRUM SHAFT | ||||
| drums until instructed to do so. |
| ||||||
|
|
|
|
| ||||
|
|
|
|
| ||||
| Cable drums are right and left. Be sure to check the |
|
| APPLY GREASE | ||||
| identification on each drum to make sure the correct |
|
| |||||
|
|
| TO DRUM SHAFT | |||||
| drum is installed on its corresponding side. |
|
| |||||
|
|
| FLANGE | |||||
| Apply grease to both sides and outer diameter of the |
|
|
|
| |||
| flange of the drum shaft. |
| CABLE DRUM | |||||
|
|
|
|
|
| |||
| Insert the |
|
|
|
| |||
| drum shaft. Then insert the screw and shaft into the |
|
|
|
| |||
| drum so that the screw threads and drum shaft are |
|
|
|
| |||
| showing out past the drum bearing. |
|
|
|
| |||
| Install the drum/shaft/screw assembly into the 3/4” |
| ||||||
| hole in the flag bracket. Be sure the end of the shaft |
| ||||||
|
| HEAD CAP SCREW | ||||||
| is inserted into the hole in the flag angle. |
| ||||||
|
|
|
|
| ||||
|
|
|
|
|
|
|
|
|
| Secure assembly with a 1/2” washer and 1/2” |
|
| DRUM SHAFT DRUM ASSEMBLY | ||||
| lock nut. |
| (SHRINK WRAPPED) | |||||
|
|
|
|
|
| 3/4” HOLE | ||
| Check to make sure the drum will rotate freely |
| FLAG | |||||
| on the shaft. If not, loosen 1/2” lock nut until the |
| BRACKET | |||||
| drum is free to rotate. Repeat for opposite side. | 1/2” WASHER |
1/2” LOCK NUT
Step 6: Bottom Bracket Lifting Cables
Locate the end of the lifting cable where the custom loop was made earlier in the instructions. Carefully pull the cable, bringing the loop to the milford pin located in the bottom bracket on the edge of the bottom section. Secure the cable loop around the milford pin, making
sure the loop is over the head of the milford pin and around the smaller diameter. Repeat for the other side.
LIFTING
CABLE
MILFORD PIN ON BOTTOM BRACKET