Generac 04077-1, 04109-1, 04079-1, 00789-1, 00844-1 manual Fuse, Post Installation Inspection

Page 19

Section 1 — Installation

Guardian Air-cooled Generators

 

 

1.17.1 BATTERY INSTALLATION

Figure 1.14 – Battery Cable Connections

 

 

 

 

 

Fill the battery with the proper electrolyte fluid if nec- essary and have the battery fully charged before installing it.

Before installing and connecting the battery, complete the following steps:

1.Set the generator's Auto/Off/Manual switch to OFF.

2.Turn off utility power supply to the transfer switch.

If the Auto/Off/Manual switch is not set to its OFF position, the generator can crank and start as soon as the battery cables are connected. If the utility power supply is not turned off, sparking can occur at the battery posts and cause an explosion.

Battery cables were factory connected at the genera- tor (Figure 1.14). Connect cables to battery posts as follows:

1.Connect the red battery cable (from starter con- tactor) to the battery post indicated by a positive, POS or (+).

2.Connect the black battery cable (from frame ground) to the battery post indicated by a nega- tive, NEG or (—).

NOTE:

With the battery installed and utility power source voltage available to the transfer switch, the battery receives a trickle charge while the engine is not running, to prevent self-discharge. The trickle charge feature cannot be used to recharge a dis- charged battery.

1.18 THE FUSE

The generator panel’s 15-amp fuse protects the DC control circuit against overload. The fuse is wired in series with the battery output lead to the panel. If the fuse element has melted open, you cannot crank or start the engine. You should replace the fuse using only an identical 15-amp replacement.

1.19 POST INSTALLATION INSPECTION

Before placing the home standby electrical system into service, inspect the entire installation carefully. Some areas may require that an inspection be per- formed by a building or electrical inspector.

Figure 1.15 – Typical Emergency Power System

Generac® Power Systems, Inc. 17

Image 19
Contents Installation, Start-up and Adjustment Manual Authorized Dealer Location Operation and MaintenanceHOW to Obtain Service IntroductionIntroduction Inside Front Cover InstallationPost-installationStart-up Adjustments TroubleshootingGeneral Hazards Electrical Hazards Unpacking Introduction to InstallationGaseous Fuel System Before InstallationLifting the Generator Engine OIL RecommendationsFuel Consumption Reconfiguring the Fuel SystemFuel Pipe Sizing Location and Mounting Transfer SwitchGenerator Installation Installation Generator Mounting Dimensions Sound Attenuated Total Circuit Isolation Method Emergency Circuit Isolation Method11.1 6 KW, 8 KW and 10 KW Units NON-SA Wiring InterconnectionsSound Attenuated Units Installation Generators and GTS Transfer Switches Grounding the Generator Adapting THREE-PHASE Transfer SwitchBattery Battery Installation Post Installation InspectionFuse OFF Position Using the AUTO/OFF/MANUALAutomatic Transfer Operation Auto PositionManual Transfer Operation Sequence Automatic OperationProtection Systems Transfer Back to Utility Power SourceLOW OIL Pressure Switch High Temperature SwitchOverspeed Approximate Crank Cycle Times1 6 KW, 8 KW and 10 KW Units NON-SA Generator Tests Under Load Check Transfer Switch OperationBefore Initial START-UP Electrical ChecksChecking Automatic Operation Adjusting the Load Block1 6 KW Units NON-SA Engine Governor Adjustment2 8 KW and 10 KW Units NON-SA Overspeed Adjustment Voltage Regulator Adjustment10.1 6 KW, 8 KW and 10 KW Units NON-SA Setting the Exercise TimerProblem Cause Correction Troubleshooting GuideInstallation Checklist Guardian Air-cooled Generators Generac Power SYSTEMS, INC