Emerson 225-600KVA installation manual Alber Monitoring System-Optional

Page 14

Battery Installation

2.6Alber Monitoring System—Optional

The Liebert matching battery cabinet allows installing an optional Alber battery monitoring system in the cabinet. The Alber battery monitoring continuously checks all critical battery parameters, such as cell voltage, overall string voltage, current and temperature. Automatic periodic tests of internal resistance of each battery will verify the battery’s operating integrity. Additional capabilities include automatic internal DC resistance tests and trend analysis providing the ability to analyze performance and aid in troubleshooting.

The Alber monitoring system is installed inside the battery cabinet (see Figure 21). The monitoring system requires approximately 0.5A, single-phase power.

This power can come from the output of the UPS the battery cabinet is suppling (see Figure 21).

The Alber monitoring system consists of a Controller Module and Data Collector Module (see Figure 19). One Controller Module can monitor up to six battery cabinets with a Data Collector Module installed. The battery cabinet with the Controller Module (Battery Cabinet #1) must be installed in the position closest to the UPS.

For details about operating the Alber system, see the Alber Monitoring System manual, available at the Liebert Web Site, www.liebert.com

2.7External Battery Room Temperature Sensor—Optional

For systems that do not use Liebert NX Battery Cabinets, an optional temperature sensor can be installed to monitor the ambient room temperature. This sensor is connected to the BIB board (see Figure 6). This sensor will allow the Liebert NX UPS to perform temperature compensation charging.

Figure 6 Battery temperature sensor control connection

Battery Interface Board

P1153

TB1154

Liebert® NX

10

Image 14
Contents Liebert NX Battery System Product Warranty Registration Table of Contents Figures Important Safety Instructions Liebert NX Environmental Considerations IntroductionPreliminary Checks Shipping bolts-Top-Terminal Battery Cabinet PositioningSystem Composition ClearancesSafety LayoutAdditional Liebert Attached Attached Liebert Additional Junction BatteryJunction Battery Cable Entry Power ConnectionAdditional Liebert Battery Cabinet Stand Alone Junction Control Connection GroundingExternal Battery Room Temperature Sensor-Optional Alber Monitoring System-OptionalBottom View Main components, Liebert Top-Terminal Battery Cabinet Do not DOUBLE-STACK Lugs Front Top View Front Ground BUS Detail Front View Terminal Details Outline DrawingLiebert NX Battery Cabinet control wiring Attached battery cabinet connections Typical Alber battery monitoring connections Battery Alber battery monitoring assembly diagram Alber battery monitoring assembly connectionsTop-Terminal battery configuration Cable Interconnect Diagram Left-Side Busbar Connections Right-Side Busbar Connections Specifications Liebert NX Battery Cabinet specificationsDC currents for Liebert NX modules Liebert NX Junction Cabinet specificationsAlber battery monitoring option specifications Liebert NX Battery Cabinet internal breaker Liebert NX Battery Cabinet approximate weightsBattery torque values UPS Rating KVA # Conduit Size, Ph, GTorque specifications, unless otherwise labeled Specifications Liebert NX Specifications Liebert NX Page Twor k Ne tIs t Care