Xantrex Technology PV-225208 Visual Inspection, Isolation Transformer WYE/WYE, Initial Power

Page 14

SECTION 3

INSTALLATION AND INITIAL TURN-ON

INITIAL TURN ON PROCEDURE

The following must be performed by an approved Technician:

The following procedures are intended to verify correct installation and proper operation of the PV-225208. These steps are to be followed sequentially. Do not continue if any of the steps or results are unclear. Refer to Section 4 for a detailed description of system operation. Refer to Section 5 for fault condition descriptions and troubleshooting. Refer to Section 7 for detailed system schematics.

Visual Inspection, Isolation Transformer WYE/WYE

Verify the isolation transformer circuit breaker is open.

If a phase rotation meter is available, verify proper phase rotation at the line side of the isolation transformer circuit breaker.

Insure the neutral on the inverter side is left floating. If the inverter side neutral is tied to ground, the inverter will not function properly. Also, insure that the neutral is not bonded to the isolation transformer frame.

Verify the inverter 208 VAC conductors are connected to the isolation transformer.

If the wires are marked, verify they follow the sequence on the line side of the isolation transformer and circuit breaker.

Verify the utility conductors are properly connected to the isolation transformer.

Visual Inspection, PV-225208

Insure AC and DC disconnect switches are opened.

Remove the front cover from the inductor enclosure, open the door of the main enclosure, and disconnect enclosures and inspect.

Verify all wire connections are tight.

Inspect the fiber optic cables between the PCU and the matrix driver boards. All fibers should be snap-locked into their respective receivers/transmitters.

Insure all connector jack screws on the PCU and matrix driver board are tight.

Verify AC phase connections landed at the AC interface enclosure.

Visual Inspection, PV Array Wiring

Verify the PV+, PV-, and PV safety ground are isolated from each other. The safety ground must not be tied to PV-.

Verify all PV fuses are installed.

Initial Power

Turn the On/Off switch, located on the front door to off.

With the DC disconnect switch opened, close one of the PV array string disconnect switches.

Carefully measure VDC across the PV +/- terminal block. The value should be the same as at the PV array string disconnect switch. It should also be positive.

Close the PV disconnect switch.

Carefully measure VDC between the DC contactor negative (-) terminal and the DC switch positive

DOCUMENT: 151811

PV-225208 Photovoltaic Inverter

3-6

 

Operation and Maintenance Manual

Copyright 2003, Xantrex Technology Inc.

Image 14
Contents Manual Table of Contents Major Components Operation and Maintenance ManualSection Product Description Introduction Main EnclosureSection Product Description Control ComponentsPower Control Unit PCU Interconnection Standards ComplianceSection Product Description Specifications Equipment SymbolFault Reporting Section Safety Safety FeaturesMain Enclosure Door Interlock Switch PV Ground Fault DetectionOver/Under Voltage and Frequency Section SafetyIsolation Procedure Anti Island ProtectionTorque and Wire Gauge Specifications Utility Side Isolation Transformer RequirementsInstallation Section Installation and Initial TURN-ONInstallation Instructions Cable Entry Area Array Grounding Interconnection Wiring Ground Fault DetectionInterface PV-225208 Inverter Wiring Diagram Chassis Gnd TransformerPV Array Frame Ground DC Interface Circuit BreakerVisual Inspection, Isolation Transformer WYE/WYE Visual Inspection, PV Array WiringInitial Power Visual Inspection, PV-225208System Verification Power Tracker Fine Tuning Operating States Section Operation Description of System OperationOverview Utility Voltage/Frequency Fault Automatic Reset Operation FeaturesFixed Unity Power Factor Operation Section OperationCurrent Imbalance Detection Peak Power TrackingOperator Interface DC Overvoltage DetectionSection Operation Manual State Transitions Commanding Goal State ChangesSetting the Date and Time Changing Write Parameter ValuesSleeping → Power Tracking → Sleeping Automatic State TransitionsAny State → Fault AUTO-RESTART FeatureTURN-ON Procedure Section Troubleshooting General Alarm and Fault ConditionsPV Overvoltage S Section TroubleshootingProgramming Mode S Bad Memory SAC Voltage Too Low S Door Interlock Switch Open HPV Auxiliary Switch Open H AC Voltage Too High SXX25/XX26 Line Gate Drive Fault S YY27/YY28 Line Over-Current Fault SPV Over-Current Fault S DC Bus Voltage High HSection Preventative Maintenance Periodic Maintenance Section Preventative Maintenance Read-Only Parameters Section Appendix Faults CodesREAD/WRITE Parameter Menu Section Appendix Inverter StatesADC Warranty and Certification Drawings ListXantrex PV Series Limited Warranty and Registration Page Page Page Page Page Fab, Enclosure, Upper, 2 Bay, PV225208 Page Fab, Enclosure, DC Interface, PV225208 Page TB5 Source Control Specification