Xantrex Technology ACCB-L manual Mounting on Plywood, To mount the Long AC Conduit Box on plywood

Page 35

Mounting

Mounting on Plywood

Mounting holes and keyhole slots for ACCB-L (x6)

Plywood

ACCB-L Base with top cover removed

Bias the screws (top and bottom) away from the inverter for easier servicing if necessary

Important: Ensure that the factory-installed cables in the Long AC Conduit Box are not pinched, crushed, removed, or damaged during the installation to the inverter.

To mount the Long AC Conduit Box on plywood:

1.With the help of another person, lift the inverter and mount it into place. Secure it to the plywood with #10 wood screws (14 total - length to penetrate 1½ inches or more into the studs.) See the Sine Wave Plus Inverter/Charger Owner’s Manual for more specific mounting instructions for the inverter.

2.Line up the Long AC Conduit Box at the AC end of the inverter, so that the mounting rails are aligned together and the Long AC Conduit Box base is as close to the inverter as possible. The gap between the Long AC Conduit Box and the inverter should be no more than 1/16 inch.

3.Secure the Long AC Conduit Box in place with six #10 wood screws of an appropriate length (or lag bolts) in the six mounting and keyhole slots on the mounting rails of the ACCB. Bias the screws away from the inverter.

4.Leave the top cover off the Long AC Conduit Box to proceed with wire connections.

Align Mounting Rails

Figure 2-10Installing the ACCB-L to the SW Plus Inverter on Plywood

973-0031-01-01 Rev A

2–13

Image 35
Contents Sine Wave Plus Long AC Conduit Box Owner’s Guide Page Sine Wave Plus Long AC Conduit Box Date and Revision Organization PurposeScope AudienceRelated Information Conventions UsedAbbreviations and Acronyms Important Safety Instructions Certifications Explosive gas precautionsContents Operation Figures Page Tables Xii Introduction 1The Sine Wave Plus ACCB-L Basic IntroductionACCB-L-L1 ACCB-L ACCB-L-L1 Specifications3ACCB-L Dimensions not to scale For more information see , Operation in this guide AC Bypass Switch Assembly5Blockoff Plates Blockoff PlatesPage Installation Code Compliance Preparing for the InstallationInstallation Tools and Materials On-Grid Configurations Configuration PlanningOff-Grid Configurations Location Pre-InstallationService Planning 12 305 mm Required Shock Hazard Warning Label Ventilation RequirementsRemoving and Replacing the Cover 3Cover Removal and Replacement4The Blockoff Plate on the Long AC Conduit Box Installing or Removing the Blockoff Plates5SW Plus Inverter, AC Side Showing Knockout Location Knockout Preparation6Knockouts Locations 7Installing Additional Breakers on the DIN Rail Installing Additional BreakersMounting on the Xantrex Back Plate XBP Mounting9Installing the ACCB-L on the Backplate To mount the Long AC Conduit Box on plywood Mounting on PlywoodWiring General 1Torque Values for Wiring Wire Sizes and Disconnect Requirements11ACCB-L Approved Internal Components 12ACCB-L-L1 Internal Components Factory installed Installation Single Inverter Configurations 120 Vac Wiring for Off-Grid ApplicationsInstallation Step-down Configurations 240 Vac to 120 Vac Installation Step-up Configuration Deep Well Pump 120 Vac to 240 Vac Dual Inverter Configurations 120 Vac and 240 Vac 20Wiring an On-grid Application Using a Single Inverter Wiring for On-Grid ApplicationsInstallation Step-up Configurations Utility Backup 120 Vac to 240 Vac Dual Inverter Configurations 120 Vac and 240 Vac 24Accessory Wiring for Single-Inverter Configurations Additional Accessory Wiring25Accessory Wiring for Dual-Inverter Configurations Operation Operating the AC Bypass Switch AC Bypass SwitchBypass Operation Normal OperationAC Input/Output Off Dual Inverters 240 Vac LoadsWarranty Warranty and Return InformationExclusions DisclaimerProduct Out of Warranty Service Return Material Authorization PolicyReturn Procedure Serial Number Purchased From Purchase Date Information About Your SystemIndex IX-2 Rev a Page Xantrex Technology Inc