Step 5. Turn the power switch on the power module to the on position. Verify that the green LED is illuminated.
The correct method for removal of a power module is as follows:
Step 1. The power switch on the rear of the power module must be in the off position. Make sure the power LED is NOT illuminated.
Step 2. Disconnect the power cord from the power module as well as the AC power source.
Step 3. Loosen the two thumb screws on the face of the power module.
Step 4. Carefully slide the power module out of the rack enclosure.
ATTO FC Rack System Installation Considerations
∙Operating Temperature – The manufacturer’s maximum rated ambient temperature is 40 C. Consideration should be given to installing the FC Rack system in an environment where this temperature could be compromised.
∙Reduced Air Flow – Consideration should be given to installing the FC Rack system in an environment where the air flow required for safe operation could be compromised.
∙Mechanical Loading – Mounting of the FC Rack system should be that no uneven mechanical loading is imposed upon the FC Rack system.
∙Circuit Overloading – Consideration should be given to the supply circuit to which the FC Rack system is connected. Overloaded supply circuits may have hazardous effects to the overcurrent protection and supply wiring and thus damage the FC Rack system and its modules. Appropriate consideration of the equipment nameplate rating should be used when addressing this concern.
∙Reliable Grounding – Reliable grounding of the rack mounted equipment should be maintained.