APC ACRC100, ACRC103 manual Than 76 l/m 20 gpm

Page 27

3. Slightly open the top coil vent.

4. At the water supply, open the appropriate valves to begin letting water slowly enter the equipment.

5. At the equipment, close the top coil vent when water begins slowly flowing out of the vent.

6. At the water supply:

 

a. Open all valves (no greater

na1768a

than 76 l/m [20 gpm]),

 

allowing the water supply to

 

reach the highest possible flow

 

to the equipment for 45 seconds.

 

b.Close the valves to a 3.8–11.4 l/m (1–3 GPM) flow for 60 seconds.

c.Open the valves to maximum flow for another 45 seconds.

d.Balance the system to provide the designed flow rate to all equipment.

Top coil vent

InRow RC Installation

21

Image 27
Contents Installation 동봉된 CD 안에 한국어 매뉴얼이 있습니다 American Power Conversion Legal Disclaimer Page Contents Mechanical Connections Safety Manual updates Cross-reference symbol used in this manualOverview Damage to Equipment or Personnel Door and side panel locks Installation kitInspecting the Equipment InventoryExterior Component IdentificationInterior User interface connection panel Room Preparation Incoming power supply requirementsWith cooling distribution unit CDU Piping DiagramsTop piping InRow Bottom piping To customer Supplied chiller Without CDUOut From Coils FullFull Bypass Open Internal piping diagramDimensions are shown in mm Piping and electrical access locationsWeights and Dimensions Door removal Side panel removal Removing Doors and PanelsService access Positioning the EquipmentLeveling Stabilizing the Equipment Floor bracketsJoining to enclosures Piping Mechanical ConnectionsConnect piping Condensate pump drain connection Chiller Accessories and spare partsFilling and Purging Than 76 l/m 20 gpm Electrical Connections Power connections Control Modbus User interface connection pinoutLink ports Network port Modbus Control connectorLeak detector port Form C alarm contacts and shutdown inputTemperature sensor 990-2402D-001 11/2012 APC Worldwide Customer Support