Liebert XDK user manual Control, Automatic Door Opening

Page 10

Description

3.3Control

The server cabinet temperature is controlled by the fan control board

A temperature sensor continuously measures the temperature of the server cabinet (server feed air). The air circulation flow rate is controlled by the fan speed according to the current thermal load.

At temperatures lower than 70°F (21°C) fans rotate at 75% of maximum speed.

Between 68°F and 73°F (20 and 23°C), speed increases proportionally to the temperature up to 96% of maximum speed.

The failure of the temperature sensor set the fans to maximum speed.

The water flow rate is controlled by a three-way valve depending on thermal load. In case of failure, the valve opens and the all the chilled water flows through the heat exchanger.

From 61°F to 66°F (16°C to 19°C), the three-way valve controls the water flow rate from 0% to 100% of the nominal flow rate.

The programming of the control is factory-set and protected with a password.

The failure of the temperature sensor or one of the fans will set off an alarm using a potential free contact.

The outgoing alarms with potential free contact are:

sensor error

fan malfunction

high-temperature / low-temperature

The fans are automatically shut down if the server cabinet rear door is opened.

3.4Automatic Door Opening

Figure 3 XDK door and automatic opening mechanism

Upper magnet

Gas pressure spring

and retaining

 

plate

 

6

Image 10
Contents UserManual-17kW Important Safety Instructions Table of Contents Figures Introduction Operating Conditions Proper ApplicationGeneral operating data General function DescriptionAir / Water Principle of Cooling OperationHeat Exchanger Data Overview-XDK Technical dataXDK general data Control Automatic Door OpeningFunction Initial CommissioningManual Closing Manual OpeningHandling Packaging MaterialEquipment INSPECTION, Handling and Storage Storage Returning the Unit in Case of DamagePositioning the XDK Preparation for InstallationInstallation and Commissioning Remove Recirculation Air Duct Transport LockWater Connection Preparing Heat Exchanger for Initial CommissioningTop View Rear Preparations for ConnectingCondensed Water Connection FrontElectrical Connection Sealing the CabinetFan Replacement Servicing and MaintenanceGeneral Inspection on Fans-Annual Reinstall the fan by reversing the steps to remove the fan Inspect the Heat Exchanger-AnnualHeat exchanger replacement Replacing the Heat ExchangerDismantling and Disposal Prevalent impurities and removal methods Water Purity RequirementsSuggested hydrologic levels Unit Installation Checklist Commissioning Certificate Nominal values at setup siteXDK Commissioning certificate Type of cabinet ConfigurationControl of status Electrical data / documents Cold water facility on siteFunction check GPM Water Purity Requirements Page Ti n Ne tIti That