Installation and Commissioning

5.3Water Connection

The heat exchanger can be pulled out for servicing

Water pipes should be connected so that the heat exchanger can be pulled out when the connection is undone. If the heat exchanger is connected to the water circuit using threaded fittings, the pipe fitting must be supported on tightening.

Before commissioning the server cabinet, the pipe connections should be checked for leaks according to local codes.

5.3.1Preparing Heat Exchanger for Initial Commissioning

Check the mechanical installation and the supply pipe connection.

Figure 6 Heat exchanger access

Remove this air duct

for bleeding, draining the heat exchanger and checking the valve

1.Carefully bleed heat exchanger when filling the system.

2.Open the air bleed valve until the water coming out has no bubbles.

3.Close this valve after bleeding.

Figure 7 Control valve

Air bleed valve

Water return

Water supply

Drain valve

4.If necessary, retighten threaded fittings.

5.After an extended period without use, and particularly in case of risk of freezing temperatures, the heat exchanger and the supply pipe must be drained of all fluid.

6.Drain completely by blowing out with compressed air and remove all bleed and drain plugs.

12

Image 16
Contents UserManual-17kW Important Safety Instructions Table of Contents Figures Introduction Operating Conditions Proper ApplicationGeneral operating data General function DescriptionAir / Water Principle of Cooling OperationHeat Exchanger Data Overview-XDK Technical dataXDK general data Control Automatic Door OpeningFunction Initial CommissioningManual Closing Manual OpeningHandling Packaging MaterialEquipment INSPECTION, Handling and Storage Storage Returning the Unit in Case of DamagePreparation for Installation Installation and CommissioningPositioning the XDK Remove Recirculation Air Duct Transport LockWater Connection Preparing Heat Exchanger for Initial CommissioningTop View Preparations for Connecting Condensed Water ConnectionRear FrontElectrical Connection Sealing the CabinetFan Replacement Servicing and MaintenanceGeneral Inspection on Fans-Annual Reinstall the fan by reversing the steps to remove the fan Inspect the Heat Exchanger-AnnualHeat exchanger replacement Replacing the Heat ExchangerDismantling and Disposal Prevalent impurities and removal methods Water Purity RequirementsSuggested hydrologic levels Unit Installation Checklist Commissioning Certificate Nominal values at setup siteXDK Commissioning certificate Type of cabinet ConfigurationControl of status Electrical data / documents Cold water facility on siteFunction check GPM Water Purity Requirements Page Ne t ItiTi n That