4.0EQUIPMENT INSPECTION, HANDLING AND STORAGE

Upon arrival of the unit, and before unpacking, verify that the labeled equipment matches the bill of lading. Inspect all items for damage, either visible or concealed. Damage should be immediately reported to the carrier and a damage claim filed with a copy sent to your local sales representative.

4.1Packaging Material

All material used to package this unit is recyclable. Please save for future use or

dispose of the material appropriately.

R

 

SAFETY INFORMATION

! WARNING

Risk of top-heavy unit falling over. Improper handling can cause equipment damage, injury or death! Read all of the following instructions before attempting to move, lift, remove packaging from or preparing unit for installation.

! WARNING

Risk of sharp edges, splinters and exposed fasteners. Can cause personal injury.

Only properly trained personnel wearing appropriate safety headgear, gloves, shoes and glasses should attempt to move, lift, remove packaging from or prepare unit for installation.

! CAUTION

Risk of overhead interference. Can cause unit and/or structure damage.

Refer to the installation plans prior to moving the unit to verify clearances.

! CAUTION

Risk of damage from fork lift! Improper handling with the forklift can cause exterior and/or underside damage! Keep tines of the fork lift level and at a height suitable to fit below the skid.

4.2Handling

When possible, transport the unit using a forklift or pallet jack. Otherwise use a crane with belts or cables.

When using a forklift or pallet jack, make sure the forks (if adjustable) are spread to the widest allowable distance that will fit under the skid.

Ensure that the fork length is suitable for the unit length.

When using a forklift while moving the packaged XDK, do not lift it higher than 6" (152mm).

If circumstances require the XDK to be lifted higher than 6" (152mm), great care must be exer- cised. Personnel not involved in moving the unit must be at least 20' (5m) from the lift point of the unit.

Belts or cables must be used when the XDK is moved with a crane.

The XDK’s net weight is 749 lb. (340 kg).

Avoid twisting the housing or other damage during handling.

Ensure that the XDK’s doors are closed prior to lifting.

Do not stand under an XDK while it is suspended.

Hooks used to attach to the unit must be of appropriate tensile strength.

The XDK must not be lifted at an angle.

9

Image 13
Contents UserManual-17kW Important Safety Instructions Table of Contents Figures Introduction Operating Conditions Proper ApplicationGeneral operating data Description General functionAir / Water Principle of Cooling OperationHeat Exchanger Data Overview-XDK Technical dataXDK general data Automatic Door Opening ControlInitial Commissioning FunctionManual Opening Manual ClosingHandling Packaging MaterialEquipment INSPECTION, Handling and Storage Returning the Unit in Case of Damage StorageInstallation and Commissioning Preparation for InstallationPositioning the XDK Remove Recirculation Air Duct Transport LockPreparing Heat Exchanger for Initial Commissioning Water ConnectionTop View Condensed Water Connection Preparations for ConnectingRear FrontSealing the Cabinet Electrical ConnectionFan Replacement Servicing and MaintenanceGeneral Inspection on Fans-Annual Inspect the Heat Exchanger-Annual Reinstall the fan by reversing the steps to remove the fanReplacing the Heat Exchanger Heat exchanger replacementDismantling and Disposal Prevalent impurities and removal methods Water Purity RequirementsSuggested hydrologic levels Unit Installation Checklist Commissioning Certificate Nominal values at setup siteXDK Commissioning certificate Type of cabinet ConfigurationControl of status Electrical data / documents Cold water facility on siteFunction check GPM Water Purity Requirements Page Iti Ne tTi n That