Liebert Preparation for Installation, Positioning the XDK, Installation and Commissioning

Page 15

Installation and Commissioning

5.0INSTALLATION AND COMMISSIONING

5.1Preparation for Installation

! CAUTION

Risk of improper installation. Can cause equipment damage.

Before installing the unit, a number of points must be checked for safety and to ensure the correct function of the server cabinet. Take care when performing these checks to ensure that the unit functions correctly.

! CAUTION

Risk of improper installation. Can cause equipment damage.

The XDK must be installed on a level surface. For this reason, check the horizontal alignment with a spirit level prior to starting installation. The floor must be able to support a rack load of 307 lb/ft² (1500 kg/m²) (with installed equipment per XDK).

To achieve good air circulation, ensure that there is no packaging material or other equipment that could hinder or prevent air circulation in the area of the equipment, in the area of the heat exchanger, in the air inlet or in the air outlet.

5.2Positioning the XDK

After positioning, the XDK’s feet must be adjusted to make the cabinet vertical. When positioned the doors must close easily.

5.2.1Remove Recirculation Air Duct Transport Lock

The Liebert XDK is shipped without the gas pressure springs for the front and rear automatic door openers installed. The springs should be installed according to separate instructions before the Lie- bert XDK is connected and turned on.

After positioning, remove the transport lock screws at the sides of the recirculation air duct (see Figure 5).

The recirculation air duct may be pulled out to remove items that fall into the heat exchanger tray.

Figure 5 Remove the transport lock screws

Remove both screws

11

Image 15
Contents UserManual-17kW Important Safety Instructions Table of Contents Figures Introduction Proper Application Operating ConditionsGeneral operating data Description General functionPrinciple of Cooling Operation Air / WaterHeat Exchanger Technical data Data Overview-XDKXDK general data Automatic Door Opening ControlInitial Commissioning FunctionManual Opening Manual ClosingPackaging Material HandlingEquipment INSPECTION, Handling and Storage Returning the Unit in Case of Damage StorageRemove Recirculation Air Duct Transport Lock Preparation for InstallationInstallation and Commissioning Positioning the XDKPreparing Heat Exchanger for Initial Commissioning Water ConnectionTop View Front Preparations for ConnectingCondensed Water Connection RearSealing the Cabinet Electrical ConnectionServicing and Maintenance Fan ReplacementGeneral Inspection on Fans-Annual Inspect the Heat Exchanger-Annual Reinstall the fan by reversing the steps to remove the fanReplacing the Heat Exchanger Heat exchanger replacementDismantling and Disposal Water Purity Requirements Prevalent impurities and removal methodsSuggested hydrologic levels Unit Installation Checklist Nominal values at setup site Commissioning CertificateXDK Commissioning certificate Configuration Type of cabinetControl of status Cold water facility on site Electrical data / documentsFunction check GPM Water Purity Requirements Page That Ne tIti Ti n