3.0DESCRIPTION

3.1General function

The modular design facilitates the installation of 19-inch-wide equipment of varying depth.

Heat produced by equipment in the cabinet, such as servers, is removed by the cold water system integrated into the server cabinet. The cooling system is isolated from the server area, protecting the sensitive equipment from water damage.

The cooling system comprises a high-performance air/water heat exchanger, fans with fan control unit, fan-speed according to heat load.

The air circuit is closed such that no heat is emitted to the environment.

! CAUTION

Risk of improper operation. Can cause equipment damage.

The XDK works only if cold server feed air and heated server outlet air are fully separated. Height units not in use must be sealed with blanking panels.

Figure 1 Cooling airflow, top view

 

Air Duct

Warm

Warm

Warm

Server

Warm

 

Cold

 

 

 

Air

 

Cold

Separation

 

 

 

Front

 

3

Image 7
Contents UserManual-17kW Important Safety Instructions Table of Contents Figures Introduction Operating Conditions Proper ApplicationGeneral operating data Description General functionAir / Water Principle of Cooling OperationHeat Exchanger Data Overview-XDK Technical dataXDK general data Automatic Door Opening ControlInitial Commissioning FunctionManual Opening Manual ClosingHandling Packaging MaterialEquipment INSPECTION, Handling and Storage Returning the Unit in Case of Damage StorageRemove Recirculation Air Duct Transport Lock Preparation for InstallationInstallation and Commissioning Positioning the XDKPreparing Heat Exchanger for Initial Commissioning Water ConnectionTop View Front Preparations for ConnectingCondensed Water Connection RearSealing the Cabinet Electrical ConnectionFan Replacement Servicing and MaintenanceGeneral Inspection on Fans-Annual Inspect the Heat Exchanger-Annual Reinstall the fan by reversing the steps to remove the fanReplacing the Heat Exchanger Heat exchanger replacementDismantling and Disposal Prevalent impurities and removal methods Water Purity RequirementsSuggested hydrologic levels Unit Installation Checklist Commissioning Certificate Nominal values at setup siteXDK Commissioning certificate Type of cabinet ConfigurationControl of status Electrical data / documents Cold water facility on siteFunction check GPM Water Purity Requirements Page That Ne tIti Ti n