Cisco Systems SFS 3001 quick start Install the Topspin 90 in an Equipment Rack, Requirements

Page 10

2

5.Prepare the physical environment for the Topspin 90.

a.Make sure that you have an approved grounding wrist-strap.

b.Make sure the system has the right cables and sufficient ventilation.

c.Unpack the Topspin 90 package, using the packing list provided.

d.Verify that you have all of the items on the Requirements list. See “Requirements” on page 2.

Install the Topspin 90 in an Equipment Rack

There are two different methods that can be used to rack the Topspin 90. This guide provides instructions for one method. To view instructions on the alternative method, refer to the Topspin 90 Hardware Guide.

Requirements

In addition to the accessories provided with the switch, you should have:

Phillips screw driver

Eight screws and any associated mounting clips to secure the brackets to your rack (2 for each rail of the rack)

Two people are recommended to perform the install

Prepare for the Installation

1.Open the shipping package, if you have not already done so. Remove the chassis, rack brackets, CD-ROM, parts bag, and documentation.

2.Place the chassis on a secure, clean surface.

3.Open the plastic bag containing mounting parts.

4.Check the slot in the rack for sufficient clearance.

5.Determine the direction that the switch will be installed and justified in the rack. The direction that you mount the switch will determine the direction that the brackets will need to be attached.

Rack Mount Installation

NOTE: There are two different ways to perform the rack installation of the Topspin 90. In this procedure, you will attach the rails to the rack before inserting the switch. This procedure is slightly easier to perform if you only have one person. Refer to the Topspin 90 Hardware Guide to view the second installation method.

Image 10
Contents Part Number OL-7712-01 Product ID Page Contents Regulatory Notices Page FCC Statement Safety Information Electrical CautionsPage General Cautions Laser CautionsContact Information Laser SpecsTopspin 90 Quick Start Prepare the SiteRack Mount Installation Install the Topspin 90 in an Equipment RackPrepare for the Installation RequirementsSeparate Brackets 3Holding Rack Bracket Against Inside of Rack Cable the Switch Install Expansion Modules OptionalConnect Management Ports Configure Basic Connectivity Topspin-90#copy running-config startup-config Enter the interface mgmt-ethernet commandTopspin-90config#interface mgmt-ethernet Assigning an Address Dynamically DhcpTopspin-90#show interface mgmt-ethernet Connect and Configure InfiniBand Hosts# mount /mnt/cdrom # cdmount ./tsinstall Install the Element Manager GUI 7Fully Installed IB Cable with Pinch ConnectorTopspinEM Launch Chassis ManagerPrograms -Topspin Element Manager -TopspinEM Configure Additional Settings Optional Configure the Ethernet Gateway Layer 2 Bridging ProcedureEnter interface ethernet slot/port Use the broadcast-forwarding commandEnter ifconfig eth# subnet# netmask # Enter interface gateway physical slot#Topspin-90#configure terminal Configure the Fibre Channel Gateway OptionalTopspin-90#show fc srp target Description keyword Topspin-90#show fc srp initiator Discover-itl keywordTopspin-90#show fc srp itl SRP ITLGateway-portmask-policy keyword Page Index