Configure the Fibre Channel Gateway (Optional)

To configure ITLs, perform the following steps:

1.Log in to your host.

2.Enter the /etc/init.d/ts_srp stop command at the host CLI to force the host to log out of any storage. You must disable connections now and enable them later in this process.

3.Enter the /usr/local/topspin/bin/vstat --verbosegrep -i guid command at the host CLI to display the host GUID.

NOTE: Record the GUID value. You will enter it repeatedly.

4.Enter the no shutdown command on your Server Switch CLI to bring up any Fibre Channel gateway cards that connect your device to FC storage. The gateway automatically discovers all storage.

Example

Topspin-90#configure terminal

Topspin-90(config)# card 6

Topspin-90(config-card-6)# no shutdown

5.(Optional) Enter the show fc srp target command to view the storage that your gateway(s) discovered.

Example

Topspin-90#show fc srp target

================================================================================

SRP Targets

================================================================================

wwpn: 21:00:00:04:cf:f6:c2:ab

wwnn: 20:00:00:04:cf:f6:c2:ab description: SRP.T10:21000004CFF6C2AB

ioc-guid: 00:05:ad:00:00:00:15:1a service-name: SRP.T10:21000004CFF6C2AB protocol-ids: 04:00:00:00:00:00:00:00:00:00

fc-address: 00:00:ef

mtu: 0

connection-type: nl-port

physical-access: 6/1

Total: 1 targets.

Topspin-90#

6.Enter the fc srp initiator command with

the GUID of the host (from step 3)

the GUID extension (always 00:00:00:00:00:00:00:00)

the auto-bindkeyword

to configure your host.

NOTE: For an initiator to successfully connect to storage, each physical FC gateway port requires a virtual port with a unique WWPN that points to the initiator. Also, the initiator requires a unique WWNN. You can configure these values manually, but we strongly recommend that you take

Image 23
Contents Part Number OL-7712-01 Product ID Page Contents Regulatory Notices Page Electrical Cautions FCC Statement Safety InformationPage Laser Cautions General CautionsLaser Specs Contact InformationPrepare the Site Topspin 90 Quick StartRequirements Install the Topspin 90 in an Equipment RackPrepare for the Installation Rack Mount InstallationSeparate Brackets 3Holding Rack Bracket Against Inside of Rack Connect Management Ports Install Expansion Modules OptionalCable the Switch Configure Basic Connectivity Assigning an Address Dynamically Dhcp Enter the interface mgmt-ethernet commandTopspin-90config#interface mgmt-ethernet Topspin-90#copy running-config startup-config# mount /mnt/cdrom Connect and Configure InfiniBand HostsTopspin-90#show interface mgmt-ethernet # cdmount ./tsinstall 7Fully Installed IB Cable with Pinch Connector Install the Element Manager GUIPrograms -Topspin Element Manager -TopspinEM Launch Chassis ManagerTopspinEM Configure Additional Settings Layer 2 Bridging Procedure Optional Configure the Ethernet GatewayEnter interface gateway physical slot# Use the broadcast-forwarding commandEnter ifconfig eth# subnet# netmask # Enter interface ethernet slot/portTopspin-90#show fc srp target Configure the Fibre Channel Gateway OptionalTopspin-90#configure terminal Description keyword Discover-itl keyword Topspin-90#show fc srp initiatorSRP ITL Topspin-90#show fc srp itlGateway-portmask-policy keyword Page Index