Cisco Systems UCSEZINFRACHSS Cisco UCS B230 Blade Servers, Cisco UCS B230 N20-B6730 Front Panel

Page 21

Overview

Blade Servers

The removable hard disks also have LEDs indicating hard disk access activity and hard disk health.

Buttons

The Reset button is just inside the chassis and must be pressed using the tip of a paper clip or a similar item. Hold the button down for five seconds and then release it to restart the server if other methods of restarting are not working.

The beaconing function for an individual server may get turned on or off by pressing the combination button and LED. See Interpreting LEDs, on page 25 for details.

The power button and LED allows you to manually take a server temporarily out of service but leave it in a state where it can be restarted quickly.

Connectors

A console port gives a direct connection to a blade server to allow operating system installation and other management tasks to be done directly rather than remotely. The port uses the KVM dongle device included in the chassis accessory kit. See KVM Cable, on page 69 for more information.

Cisco UCS B230 Blade Servers

For full service and installation instructions, see the Cisco UCS B230 Blade Server Installation and Service Note. You can install up to eight UCS B230 Blade Servers to a chassis.

Figure 4: Cisco UCS B230 (N20-B6730) Front Panel

1

SSD 1

Activity LED

9

Beaconing LED and button

2

SSD 1

Fault/Locate LED

10

System Activity LED

3

SSD sled in Bay 1

11

Blade health LED

4

SSD 2

Activity

12

Reset button access

Cisco UCS 5108 Server Chassis Installation Guide

OL-20035-05

9

Image 21
Contents First Published June 10 Cisco UCS 5108 Server Chassis Installation GuidePage N T E N T S OL-20035-05 Installation Installing and Removing Components Site Planning and Maintenance Records Viii Audience ConventionsText Type Indication String Documentation Roadmaps Other Documentation Resources Related Cisco UCS DocumentationXii System Overview OverviewFeature Benefit Features and BenefitsFeature Cisco UCS 5108 Server Chassis ComponentsCisco UCS B200 Blade Servers Blade ServersLEDs Cisco UCS B200 M3 Cisco UCS B200 M3 Blade ServersCisco UCS B22 M3 Cisco UCS B22 M3 Blade ServersCisco UCS B230 N20-B6730 Front Panel Cisco UCS B230 Blade ServersOL-20035-05 Cisco UCS B250 Cisco UCS B250 Blade ServersCisco UCS B440 Cisco UCS B440 Blade ServersCisco UCS B420 M3 Cisco UCS B420 M3 High Performance Blade ServerAdapter Cards Cisco UCS Virtual Interface CardCisco UCS M81KR Virtual Interface Card Cisco UCS M71KR-E Emulex Converged Network Adapter Cisco UCS 82598KR-CI 10 Gigabit Ethernet AdapterCisco UCS M71KR-Q QLogic Converged Network Adapter Cisco UCS 2104 IO Module Cisco UCS 2104XP FEXesCisco UCS 2208 FEX UCS-IOM-2208XP Cisco UCS 2200 Series FEXesCisco UCS 2204XP FEX Power Distribution Unit PDU Buttons and Connectors Power SuppliesPower Supply Redundancy Fan ModulesNon-redundant Mode Grid Redundancy LEDsLEDs on a Cisco UCS 5108 Server Chassis-Front View LED LocationsColor Description Interpreting LEDsPower Supply Blade Server LEDs OL-20035-05 Installation Cable Management Rack RequirementsCable Management Airflow ConsiderationsMoving Server Chassis Installation GuidelinesUnpacking and Inspecting the Chassis Required EquipmentAttaching the Round Hole Adapter Optional Attaching the Round Hole Adapter Kit to the Rails OptionalQuantity Part Description Installing the ChassisAdjusting the Tool-less Rack Mount Rail Installing the RailsInstalling Tool-less Chassis Support Rails into the Rack Proper Placement for the Rails and Cage Nuts Left rail Right rail Installing the Round Hole Adapter KitAttaching the Mounting Brackets to a Round Hole Rack Round Hole Adapter and Rails Installed in a Rack Inserting the Chassis into the Rack Mounting Rail Weight Distribution Square Hole Mount ShownSecuring the Chassis Into the Rack Connecting a DC Power Supply DC Power Installation ProcedureRequired Tools Procedure Inch holes measuring .625 inches from center to center Port Groups for Fabric Port Channels Cabling Considerations for Fabric Port ChannelsProper FEX and Fabric Interconnect Port Connectivity Fabric Interconnect B Rear Port Removing the Chassis from a Rack SFP+ Transceivers Repacking the ChassisSFP+ Twinax Copper Transceivers Model DescriptionSFP-10G-SR Optical SFP+ TransceiversRemoving a Twinax Copper SFP+ Transceiver OL-20035-05 Installing and Removing Components View of Cisco UCS 5108 Server Chassis Installing and Removing a Blade Server Hard Drive Installing and Removing a Blade ServerInstalling a Blade Server Hard Drive Removing a Blade Server Hard Drive Installing and Removing Power SuppliesPositioning a Power Supply in the Cisco UCS Server Chassis Installing a Power SupplyPower Supply Bay and Connector Numbering AC Version Shown Removing a Power SupplyInstalling a PDU Installing and Removing a Power Distribution Unit PDUInstalling and Removing FEXes FEX Upgrade ConsiderationsRemoving a PDU Removing a FEX Positioning a 4 Port FEX within the Server Chassis Installing a FEXInstalling a Fan Module Installing and Removing a Fan ModuleRemoving a Fan Module OL-20035-05 KVM Cable Technical SpecificationsDescription Specification Chassis SpecificationsParameter Symbol Min Max Environmental SpecificationsAC-input Gold Power Supply N20-PAC5-2500W Specifications DC-Input Power Supply N20-DC-2500 Specifications Australia and New Zealand Supported AC Power Cords and PlugsContinental Europe InternationalIsrael Japan and North America Non-Locking 200 to 240 VAC operationLocking 200 to 240 VAC Operation Switzerland Peoples Republic of ChinaCAB-ACS-16 Power Cord for the UCS 5108 Blade Server Chassis Task No. Planning Activity Verified By Time Site Preparation ChecklistTask No. Planning Activity Verified By Time Contact and Site Information Chassis and Module InformationDevice Serial Number Device Serial Number Connected to FEX Port Connection RecordPort Fabric Slot Or BOL-20035-05