Orthogonal setout | Cartesian setout |
The position offset between | dHeight: Height offset: | |
measured point and setout point | positive if point to be | |
is indicated in a longitudinal and | setout is higher than | |
transversal element. | measured point. | |
|
|
|
|
|
|
|
|
|
|
|
|
Setting out is based on a coordinate system and the offset is divided into a north and east element.
dLength: Longitudinal offset: positive if nominal point further away.
dTrav.: Transversal offset, perpendicular to
dEast | Easting offset |
| between setout and |
| actual point. |
dNorth | Northing offset |
| between setout and |
| actual point. |
dHeight: | Height offset: |
| positive if point to be |
| setout is higher than |
| measured point. |
TPS400 Mining | 28 | Setting out |
|