American Power Conversion InfraStruXureTM System manual Total Power Off, Emergency Power Off EPO

Page 13

Safety: Warnings

Total Power Off

1.Set the Symmetra PX UPS System Enable switch to Off.

2.Set the DC Disconnect breaker of each Battery Enclosure to Off.

3.Set the PDU Main Input (A) switch to Off.

4.If applicable, set the PDU Bypass Input (B) switch to Off.

5.If applicable, set the PDU Cross Tie Output (X) circuit breaker to Off.

6.Set all upstream utility circuit breakers feeding the PDU to Off.

7.Disconnect the batteries in the Battery Enclosure and any XR Battery Enclosures by pulling them out to the red disconnect line.

DANGER—Risk of Electric Shock!

Electrical Hazard

Hazardous, live parts may exist inside the PDU because of the Symmetra PX UPS inverter even when the AC power is disconnected. Test any electrical parts before touching them.

Emergency Power Off (EPO)

Hazardous voltage from the branch circuit must be isolated from the 24VAC, 24VDC, and contact closure. 24VAC and 24VDC are considered Class 2 circuits as defined in Article 725 of the National Electrical Code (NFPA 70) and Section 16 of the Canadian Electrical Code (C22.1).

A Class 2 circuit is a source having limited voltage and energy capacity as follows:

a.If an Inherently Limited Power Source, voltage and energy are limited to less than 30VAC, less than 30VDC, and 8A.

b.If not an Inherently Limited Power Source, voltage and energy are limited to less than 30VAC, less than 60VDC, 250VA, and the current is limited to 1000/Vmax. The fuse is limited to 5A if less than 20VAC or 20VDC, or 100/Vmaximum if less than 30VAC or 60VDC.

If you choose to use a 24VAC, 24VDC, or contact closure connection to the EPO, use one of the following UL-listed wire types:

CL2 Class 2 cable for general purpose use

CL2P Plenum cable for use in ducts, plenums, and other space used for environmental air

CL2R Riser cable for use in a vertical run shaft from floor to floor

CL2X Limited Use cable for use in dwellings and for use in a raceway

For installation in Canada, the cable should be CSA Certified, type ELC (extra-low-voltage control cable).

If you do not use a CL2 cable, route the EPO wiring in conduit that does not contain any branch circuit wiring.

InfraStruXure System—Installation and Start-Up

3

Image 13
Contents Installation and Start-Up Page Page Page About this Manual Page Contents Installation Procedures Appendix a System Operation Page Cross-reference symbols used in this manual Safety symbols used in this manualOverview Maintenance performed while the PDU is receiving input power Installation/MaintenanceEmergency Power Off EPO Total Power OffEMI InfraStruXure PDU DimensionsSymmetra PX UPS NetShelter VX Enclosure Battery EnclosureRack Distribution Panel Space Considerations Component Maximum Weight Weight ConsiderationsSymmetra PX UPS Heat OutputProcedures requiring a licensed electrician Electrical Requirements and SpecificationsElectrical requirements Overview Cross Tie Output Circuit BreakerPduups Emergency Power Off EPOBasic Installation Procedure Licensed electrician must connect utility power Start the system Tool Supplied? Tools RequiredInfraStruXure System-Installation and Start-Up Level the PDU, UPS, RDP, NetShelter and Battery Enclosures Installation ProceduresExchange Side Panels Connect Battery Enclosure communication cables Attach the PDU, UPS, and Battery Enclosure How to ensure that all power is off Ensure that All Power is OffInstallation Procedures Ensure that All Power is Off Connect Utility Conductors to the PDU Connect AC Power and Control Wiring Equipment Connect control wiring Jumper wire must be installed in position 13 Connect DC Power Wiring UPS Cascade Battery EnclosuresBattery Enclosure Symmetra PX UPS EPO Connect an Emergency Power Off SwitchContact Closure-Normally Open Problem Action Safety warnings ATS 0 ATS 1 ATS ATS EN Relay output specifications How to connect contacts to the PDU monitoring unitInfraStruXure System-Installation and Start-Up Cable Ladders for overhead wiring across rows Install the Rack Automatic Transfer Switches ATS Install InfraStruXure Rack-Mount DevicesInstall the Rack Power Distribution Units PDU Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racks Installation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Connect network cables to components Route Data Cables to the InfraStruXure Manager Hub or SwitchOverhead routing Page Ensure that all power is off Start-Up ProcedureStart-Up Procedure InfraStruXure System Use two people to lift and install battery units Apply power to the systemStart-Up Procedure InfraStruXure System PowerView RM Rev 000 English Please wait Verify UPS battery operation UPS load is on Press any key Verify proper voltage and phase rotation on the PDU Start the UPS PowerView RM Rev 000 English Please wait Close turn on the Q2 circuit breaker on the PDU Page Start-Up Procedure InfraStruXure System Page Power the PDU Distribution Circuit Breakers Close Cross-Tie Configure the InfraStruXure Manager Page Appendix a System Operation How to Transfer the UPS into Maintenance Bypass OperationAppendix a System Operation UPS is now in maintenance bypass operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort How to Ensure Total Power Off Appendix a System Operation How to Apply Power to the System Fuel% Load% 208V out000V 60Hz Runtime 1hr 2m Top-Level Status Screen Appendix a System Operation Appendix Appendix B Single Appendix B Single-Line Diagrams Page Changes by page number General changesPage Index InfraStruXure System-Installation and Start-Up UPS Page Page 990-1467B