American Power Conversion InfraStruXureTM System Route and attach power cables to equipment racks

Page 53

Installation Procedures: Route and Attach Overhead Wiring

Route and attach power cables to equipment racks

If you ordered overhead wiring, connect the prewired power cables of the InfraStruXure PDU as follows:

1.Install the Shielding Troughs, Shielding Partitions, and Cable Ladders so that you can route power cables from the PDU to the NetShelter VX Enclosures.

For installation instructions, see page 39.

2.Find the numbers that indicate the enclosure to which each power cable will supply power. These numbers appear on the roof of the PDU where the power cables exit, and on the ends of each power cable.

 

The enclosures are not numbered. Consult your APC InfraStruXure

 

Configuration Build-out Tool to determine the enclosure associated with each

Note

power cable.

 

3.Beginning with the power cables for the enclosures farthest from the PDU, run each power cable within the Shielding Trough along the row and, if necessary, across one or more Cable Ladders to the enclosure to which it will provide power.

Ensure that the L21-20 twist-lock connector at the end of each power cable always lies on top of any longer power cables in the Shielding Trough.

Note

4.Connect the appropriate power cable to APC power management equipment in the enclosure in one of the four following ways:

For single-feed devices without redundancy: attach a power cable directly to a Rack PDU installed in a NetShelter VX Enclosure.

InfraStruXure System—Installation and Start-Up

43

Image 53
Contents Installation and Start-Up Page Page Page About this Manual Page Contents Installation Procedures Appendix a System Operation Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Maintenance performed while the PDU is receiving input power Installation/MaintenanceEmergency Power Off EPO Total Power OffEMI Symmetra PX UPS DimensionsInfraStruXure PDU NetShelter VX Enclosure Battery EnclosureRack Distribution Panel Space Considerations Component Maximum Weight Weight ConsiderationsSymmetra PX UPS Heat OutputElectrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician Overview Cross Tie Output Circuit BreakerPduups Emergency Power Off EPOBasic Installation Procedure Licensed electrician must connect utility power Start the system Tool Supplied? Tools RequiredInfraStruXure System-Installation and Start-Up Level the PDU, UPS, RDP, NetShelter and Battery Enclosures Installation ProceduresExchange Side Panels Connect Battery Enclosure communication cables Attach the PDU, UPS, and Battery Enclosure How to ensure that all power is off Ensure that All Power is OffInstallation Procedures Ensure that All Power is Off Connect Utility Conductors to the PDU Connect AC Power and Control Wiring Equipment Connect control wiring Jumper wire must be installed in position 13 Connect DC Power Wiring UPS Cascade Battery EnclosuresBattery Enclosure Symmetra PX UPS EPO Connect an Emergency Power Off SwitchContact Closure-Normally Open Problem Action Safety warnings ATS 0 ATS 1 ATS ATS EN Relay output specifications How to connect contacts to the PDU monitoring unitInfraStruXure System-Installation and Start-Up Cable Ladders for overhead wiring across rows Install the Rack Automatic Transfer Switches ATS Install InfraStruXure Rack-Mount DevicesInstall the Rack Power Distribution Units PDU Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racks Installation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Connect network cables to components Route Data Cables to the InfraStruXure Manager Hub or SwitchOverhead routing Page Ensure that all power is off Start-Up ProcedureStart-Up Procedure InfraStruXure System Use two people to lift and install battery units Apply power to the systemStart-Up Procedure InfraStruXure System PowerView RM Rev 000 English Please wait Verify UPS battery operation UPS load is on Press any key Verify proper voltage and phase rotation on the PDU Start the UPS PowerView RM Rev 000 English Please wait Close turn on the Q2 circuit breaker on the PDU Page Start-Up Procedure InfraStruXure System Page Power the PDU Distribution Circuit Breakers Close Cross-Tie Configure the InfraStruXure Manager Page Appendix a System Operation How to Transfer the UPS into Maintenance Bypass OperationAppendix a System Operation UPS is now in maintenance bypass operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort How to Ensure Total Power Off Appendix a System Operation How to Apply Power to the System Fuel% Load% 208V out000V 60Hz Runtime 1hr 2m Top-Level Status Screen Appendix a System Operation Appendix Appendix B Single Appendix B Single-Line Diagrams Page Changes by page number General changesPage Index InfraStruXure System-Installation and Start-Up UPS Page Page 990-1467B