American Power Conversion InfraStruXureTM System manual Close Cross-Tie

Page 74

Start-Up Procedure: InfraStruXure System

Close Cross-Tie

1.If applicable, ensure A-B-C clockwise rotation at the bottom of the PDU cross tie output circuit breaker, using a phase rotation meter.

2. If applicable, verify that there is NO voltage present across the PDU cross tie circuit breaker, and that proper voltage is present on each side of the circuit breaker (208V, metered phase-to- phase), using a true RMS voltmeter.

There should be no voltage present across the Cross Tie Output circuit breaker.

Warning

3 . If applicable, set the PDU Cross-Tie Output (X) circuit breaker to ON.

Once the cross-tie output circuit breaker is closed, you can start the system to which the circuit breaker is tied. Repeat this start-up procedure for each InfraStruXure system.

64

InfraStruXure System—Installation and Start-Up

Image 74
Contents Installation and Start-Up Page Page Page About this Manual Page Contents Installation Procedures Appendix a System Operation Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Installation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPOEMI Symmetra PX UPS DimensionsInfraStruXure PDU Battery Enclosure NetShelter VX EnclosureRack Distribution Panel Space Considerations Weight Considerations Component Maximum WeightHeat Output Symmetra PX UPSElectrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician Cross Tie Output Circuit Breaker OverviewEmergency Power Off EPO PduupsBasic Installation Procedure Licensed electrician must connect utility power Start the system Tools Required Tool Supplied?InfraStruXure System-Installation and Start-Up Installation Procedures Level the PDU, UPS, RDP, NetShelter and Battery EnclosuresExchange Side Panels Connect Battery Enclosure communication cables Attach the PDU, UPS, and Battery Enclosure Ensure that All Power is Off How to ensure that all power is offInstallation Procedures Ensure that All Power is Off Connect Utility Conductors to the PDU Connect AC Power and Control Wiring Equipment Connect control wiring Jumper wire must be installed in position 13 Connect DC Power Wiring Cascade Battery Enclosures UPSBattery Enclosure Symmetra PX UPS Connect an Emergency Power Off Switch EPOContact Closure-Normally Open Problem Action Safety warnings ATS 0 ATS 1 ATS ATS EN How to connect contacts to the PDU monitoring unit Relay output specificationsInfraStruXure System-Installation and Start-Up Cable Ladders for overhead wiring across rows Install the Rack Power Distribution Units PDU Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches ATS Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racks Installation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Route Data Cables to the InfraStruXure Manager Hub or Switch Connect network cables to componentsOverhead routing Page Start-Up Procedure Ensure that all power is offStart-Up Procedure InfraStruXure System Apply power to the system Use two people to lift and install battery unitsStart-Up Procedure InfraStruXure System PowerView RM Rev 000 English Please wait Verify UPS battery operation UPS load is on Press any key Verify proper voltage and phase rotation on the PDU Start the UPS PowerView RM Rev 000 English Please wait Close turn on the Q2 circuit breaker on the PDU Page Start-Up Procedure InfraStruXure System Page Power the PDU Distribution Circuit Breakers Close Cross-Tie Configure the InfraStruXure Manager Page How to Transfer the UPS into Maintenance Bypass Operation Appendix a System OperationAppendix a System Operation UPS is now in maintenance bypass operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort How to Ensure Total Power Off Appendix a System Operation How to Apply Power to the System Fuel% Load% 208V out000V 60Hz Runtime 1hr 2m Top-Level Status Screen Appendix a System Operation Appendix Appendix B Single Appendix B Single-Line Diagrams Page General changes Changes by page numberPage Index InfraStruXure System-Installation and Start-Up UPS Page Page 990-1467B