American Power Conversion InfraStruXureTM System manual PowerView RM Rev 000 English Please wait

Page 68
Fuel %
Load %
In 208V out000V 60Hz Runtime: 1hr 2m
Top-Level Menu
Control Logging
Status Display
Setup Diags
Accessories Help
Control Menu
UPS Into Bypass Do Self Test Simulate Power Fail Graceful Reboot
Graceful Turn Off
Start Runtime Cal Turn Load On
Confirmation Screen
Confirm
Yes, UPS Load ON No, Abort
UPS has been
commanded to turn load power on...
Top-Level Status Screen

Start-Up Procedure: InfraStruXure System

When the System Enable switch is in the ON position, the UPS is running on battery. The Startup screen appears on the display interface of the Symmetra PX UPS, and then

PowerView RM

Rev: 000 English

Please wait...

the top-level status screen appears on the display interface. This may take up to 40 seconds.

Fuel %

Load %

In 208V out000V 60Hz

Runtime: 1hr 2m

3. Read the messages displayed on the Symmetra PX UPS display interface: Note any alarms and verify that they are

appropriate for start-up conditions.

4. Command the UPS to apply power to the load: a. Press the ESC key to open the top-level

menu.

b. Select Control, and press the ENTER key.

c. Select Turn Load On/Off from the Control menu, and press the ENTER key.

d. On the next screen: select Yes, UPS Load ON, and press the ENTER key.

The interface will display the following screen:

58

InfraStruXure System—Installation and Start-Up

Image 68
Contents Installation and Start-Up Page Page Page About this Manual Page Contents Installation Procedures Appendix a System Operation Page Overview Safety symbols used in this manualCross-reference symbols used in this manual Installation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPOEMI Symmetra PX UPS DimensionsInfraStruXure PDU Battery Enclosure NetShelter VX EnclosureRack Distribution Panel Space Considerations Weight Considerations Component Maximum WeightHeat Output Symmetra PX UPSElectrical requirements Electrical Requirements and SpecificationsProcedures requiring a licensed electrician Cross Tie Output Circuit Breaker OverviewEmergency Power Off EPO PduupsBasic Installation Procedure Licensed electrician must connect utility power Start the system Tools Required Tool Supplied?InfraStruXure System-Installation and Start-Up Installation Procedures Level the PDU, UPS, RDP, NetShelter and Battery EnclosuresExchange Side Panels Connect Battery Enclosure communication cables Attach the PDU, UPS, and Battery Enclosure Ensure that All Power is Off How to ensure that all power is offInstallation Procedures Ensure that All Power is Off Connect Utility Conductors to the PDU Connect AC Power and Control Wiring Equipment Connect control wiring Jumper wire must be installed in position 13 Connect DC Power Wiring Cascade Battery Enclosures UPSBattery Enclosure Symmetra PX UPS Connect an Emergency Power Off Switch EPOContact Closure-Normally Open Problem Action Safety warnings ATS 0 ATS 1 ATS ATS EN How to connect contacts to the PDU monitoring unit Relay output specificationsInfraStruXure System-Installation and Start-Up Cable Ladders for overhead wiring across rows Install InfraStruXure Rack-Mount Devices Install the Rack Automatic Transfer Switches ATSInstall the Rack Power Distribution Units PDU Install the InfraStruXure Manager and Hub or SwitchRoute and Attach Overhead Wiring Route and attach power cables to equipment racks Installation Procedures Route and Attach Overhead Wiring Installation Procedures Route and Attach Overhead Wiring Route Data Cables to the InfraStruXure Manager Hub or Switch Connect network cables to componentsOverhead routing Page Start-Up Procedure Ensure that all power is offStart-Up Procedure InfraStruXure System Apply power to the system Use two people to lift and install battery unitsStart-Up Procedure InfraStruXure System PowerView RM Rev 000 English Please wait Verify UPS battery operation UPS load is on Press any key Verify proper voltage and phase rotation on the PDU Start the UPS PowerView RM Rev 000 English Please wait Close turn on the Q2 circuit breaker on the PDU Page Start-Up Procedure InfraStruXure System Page Power the PDU Distribution Circuit Breakers Close Cross-Tie Configure the InfraStruXure Manager Page How to Transfer the UPS into Maintenance Bypass Operation Appendix a System OperationAppendix a System Operation UPS is now in maintenance bypass operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort How to Ensure Total Power Off Appendix a System Operation How to Apply Power to the System Fuel% Load% 208V out000V 60Hz Runtime 1hr 2m Top-Level Status Screen Appendix a System Operation Appendix Appendix B Single Appendix B Single-Line Diagrams Page General changes Changes by page numberPage Index InfraStruXure System-Installation and Start-Up UPS Page Page 990-1467B