
Start-Up Procedure: InfraStruXure System
3.Open (turn OFF) the Q3 circuit breaker on the InfraStruXure PDU. The UPS automatically returns from Static Bypass.
Power the PDU Distribution Circuit Breakers
1. Ensure that the Q2 circuit breaker on the PDU is closed (ON).
When Q2 is closed, the PDU distribution panel is energized.
Note
2. Close (turn ON) the PDU distribution panel circuit breakers.
When the distribution panel circuit breakers are closed, the PDU power cables and connected equipment are energized.
Note
InfraStruXure | 63 |