American Power Conversion PDRPPH1000, PD60H5HK1 Top-level status screens, Top-level menu screen

Page 14

PDU Display Interface

Top-level status screens

After displaying a brief start-up screen after system start-up, the display interface scrolls automatically and continuously through four screens of basic status information. Press the Up and Down arrow keys to interrupt the automatic scrolling to view a specific status screen.

 

 

 

Volts In

Volts Out

L1-2: 000

L1: 000

L2-3: 000

L2: 000

L3-1: 000

L3: 000

 

 

 

 

Total Output Loading

kW:

000

PF: 000

kVA:

000

%LD: 000

Freq:

00.0

 

 

 

 

Load Current

L1: 000 Neut:000

L2: 000

L3: 000

No Active Alarms

System Date/Time:

Jun-24 2003 07:58

Top-level menu screen

On any top-level status screen, press the ENTER key to open the top-level menu screen.

 

 

 

 

 

 

Load-Meter

Alarms

 

 

Volt-Meter

Panel

 

 

Contacts

Config

 

 

Breakers

Help

 

 

 

 

If the display interface is inactive for the time specified as the Time-outsetting, the interface reverts to the initial basic monitoring screens.

Note

For descriptions of the top-level menu choices, see the individual sections starting on page 8.

Navigating through screens

To open any screen, press the Up and Down arrow keys until the selector arrow ( rests next to your desired selection. Press the ENTER key to view the selected screen.

 

 

 

 

 

 

Load-Meter

Alarms

 

 

 

 

-Meter

Panel

 

 

Breakers

Config

 

 

Help

 

 

 

 

Contacts In: 02of04

Name: User Switch #2

Normal:Open

Status: Open

When configuring settings, press the Up and Down arrow keys until the selector arrow ( rests next to the setting you want to change, and press the ENTER key. If the setting is a list of choices, an input arrow ( will appear next to the setting. Press the Up and Down arrow keys until your desired change is listed. Press the ENTER key to select the setting.

Contacts In: 02of04

Name: User Switch #2

Normal:Open

Status: Open

6

60kW InfraStruXure PDU—Operation and Configuration

Image 14
Contents 60kW InfraStruXure PDU Page Audience How to find updates to this manualAbout This Manual Companion manualsPage Contents Overview Communication Configuration Product Information Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewUnpacking/moving Installation/maintenanceTotal Power Off Emergency Power Off EPO Page PDU Display Interface       Navigating through screens Top-level status screensTop-level menu screen Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Input Contacts Contacts ScreenOverview Open or ClosedPDU Display Interface How to connect contacts to the PDU monitoring unit Breakers Screen Main InputEntire Log Alarms ScreenNew Logged Items Clear LogLoading Limits Global AlarmConfig Voltage LimitsPDU Alarms Alarm Condition ExplanationBranch Ckt Limits Panel ScreenBranch Ckt Loading On the top right distribution panel Panel ConfigurationAssociated circuit breakers occupying positions 08, 10, Global Panel Config System/Network Config ScreenSystem Password Date/TimeOutput Config Electrical ConfigInput Config Manufacturer DataSystem ID Factory DefaultsFirmware Updates Front view OverviewInfraStruXure PDU Front view interior Rear view of PDU with transformer interior Rear view of PDU without transformer interior Arm/Test rocker switch PDU monitoring unitUser connection plate System Operation How to Apply Power to the SystemPower the PDU distribution circuit breakers How to Ensure Total Power Off For PDU with transformer Open turnInfraStruXure Manager Communication ConfigurationInfraStruXure PDU Management Options Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConnect the InfraStruXure PDU to your network Configuring the Network Management InterfaceConfiguration Overview TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleUse apc for the User Name and Password Choose Network from the Control Console menu Use apc for both User Name and PasswordControl console Web interface Snmp FTP and SCP 60kW InfraStruXure PDU-Operation and Configuration Important Safety Instructions Customizing and Updating the PDUBreakers Power CablesPDU Orderable Part List Add a circuit breaker on the PDU How to Add Circuit Breakers and Power CablesAdd a power cable to the PDU Customizing and Updating the PDU Overview How to connect contacts to the PDU monitoring unit How to Test the Emergency Power Off Switch Contact closure 24VAC 24VDC Contact closure is recommendedTesting the switch On the previous page for proper Upgrading the PDU monitor processor How to Download Firmware UpgradesDownloading firmware upgrades from a local computer Xmodem Page Specifications Electrical With Transformer Without TransformerCompliance InfraStruXure Standard Warranty Product InformationProduct Information APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to Contact APCChanges by page number Appendix a Changes in This ManualGeneral changes Page Index SSH Page Page Page APC Worldwide Customer Support