American Power Conversion PDRPPH1000 Panel Configuration, On the top right distribution panel

Page 26
Panel Configuration Select Range: [01..41] [02..42]

PDU Display Interface

Panel Configuration

Configure the branch metering settings for each circuit breaker on the distribution panel, or configure both panels simultaneously. To configure a circuit breaker, select the range that includes the circuit breaker. The top line of selections on the screen apply to

the top distribution circuit breaker panel on the PDU. The bottom line of selections apply to the bottom distribution circuit breaker panel on the PDU. The panel position numbers on the screen correspond to the numbers on the distribution panel. (Odd numbers are on the left; even numbers are on the right.) Once you have selected the correct range, configure the settings for each circuit breaker in the range:

Pos: The panel positions in the selected range.

Breaker: Two configurable items:

The circuit breaker rating, in amps.

The circuit breaker tie indicator: Define the number of associated panel positions. You can associate positions with circuit breakers, which enables you to view status about each circuit breaker and receive alarm notification when any of a circuit breaker’s poles are above or below the configured branch circuit limit. You can also associate together panel positions that are logically tied together. For example, you can associate together panel positions for three separate circuit breakers that are connected to the same PDU power cord and that feed power to the same equipment enclosure.

To configure the values on this screen:

1.From the first column, use the arrow keys to scroll up or down to the pole position you want to configure.

2.Press the ENTER key to move to the item you want to configure in the third column (the circuit breaker rating or the circuit breaker tie indicator).

3.Scroll again to select the value you want for the circuit breaker rating or the circuit breaker tie indicator. To associate one panel position with the next position in the list, choose the + character as the tie indicator immediately following the circuit breaker rating. To indicate that the position is not associated with the next panel position in the list, choose the ] character as the tie indicator immediately following the circuit breaker rating. When you change the + or ] character that follows the circuit breaker rating in one row, the + or [ character before the circuit breaker rating in the next row also changes to indicate the changed association between the panel positions.

For example, this screen shows three, single-pole, 16A,

associated circuit breakers occupying positions 08, 10, and

 

Pos

Breaker

 

08

[

16A

+

12 on the top right distribution panel.

10

+

16A

+

12

+ 16A ]

18

60kW InfraStruXure PDU—Operation and Configuration

Image 26
Contents 60kW InfraStruXure PDU Page Audience How to find updates to this manualAbout This Manual Companion manualsPage Contents Overview Communication Configuration Product Information Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewUnpacking/moving Installation/maintenanceTotal Power Off Emergency Power Off EPO Page PDU Display Interface       Navigating through screens Top-level status screensTop-level menu screen Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Input Contacts Contacts ScreenOverview Open or ClosedPDU Display Interface How to connect contacts to the PDU monitoring unit Breakers Screen Main InputEntire Log Alarms ScreenNew Logged Items Clear LogLoading Limits Global AlarmConfig Voltage LimitsPDU Alarms Alarm Condition ExplanationBranch Ckt Limits Panel ScreenBranch Ckt Loading On the top right distribution panel Panel ConfigurationAssociated circuit breakers occupying positions 08, 10, Global Panel Config System/Network Config ScreenSystem Password Date/TimeOutput Config Electrical ConfigInput Config Manufacturer DataSystem ID Factory DefaultsFirmware Updates Front view OverviewInfraStruXure PDU Front view interior Rear view of PDU with transformer interior Rear view of PDU without transformer interior Arm/Test rocker switch PDU monitoring unitUser connection plate System Operation How to Apply Power to the SystemPower the PDU distribution circuit breakers How to Ensure Total Power Off For PDU with transformer Open turnInfraStruXure Manager Communication ConfigurationInfraStruXure PDU Management Options Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConnect the InfraStruXure PDU to your network Configuring the Network Management InterfaceConfiguration Overview TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleUse apc for the User Name and Password Choose Network from the Control Console menu Use apc for both User Name and PasswordControl console Web interface Snmp FTP and SCP 60kW InfraStruXure PDU-Operation and Configuration Important Safety Instructions Customizing and Updating the PDUBreakers Power CablesPDU Orderable Part List Add a circuit breaker on the PDU How to Add Circuit Breakers and Power CablesAdd a power cable to the PDU Customizing and Updating the PDU Overview How to connect contacts to the PDU monitoring unit How to Test the Emergency Power Off Switch Contact closure 24VAC 24VDC Contact closure is recommendedTesting the switch On the previous page for proper Upgrading the PDU monitor processor How to Download Firmware UpgradesDownloading firmware upgrades from a local computer Xmodem Page Specifications Electrical With Transformer Without TransformerCompliance InfraStruXure Standard Warranty Product InformationProduct Information APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to Contact APCChanges by page number Appendix a Changes in This ManualGeneral changes Page Index SSH Page Page Page APC Worldwide Customer Support